IIA-ACCA practice question 26 of 35

When creating the internal audit plan, the chief audit executive should prioritize engagements based primarily on which of the following?

Full set: 604 questions
Answer options
A: The last available risk assessment. Correct answer
B: Requests from senior management and the board.
C: The longest interval since the last examination of each audit universe item.
D: The auditable areas required by regulatory agencies.
Correct Answer:
A. The last available risk assessment.