IIA-CIA-PART3 practice question 6 of 35

An internal audit engagement team found that the risk register of the project under review did not include significant risks identified by the…

Choose your answer, then check it against the explanation.

An internal audit engagement team found that the risk register of the project under review did not include significant risks identified by the internal audit function. The project manager explained that risk register preparations are facilitated by risk managers and that each project’s risk review follows the same set of questions. Which of the following recommendations will likely add the greatest value to the project management process of the organization?
Answer options