ISO-31000-CLA practice question 26 of 35

Which step is the risk process steps to manage, control, or remediate risk?

Full set: 100 questions
Answer options
A: Risk avoidance
B: Risk identification
C: Risk evaluation
D: Risk treatment Correct answer
Correct Answer:
D. Risk treatment
Explanation

Risk treatment is the specific step in the ISO 31000 risk management process focused on selecting and implementing options for addressing identified and evaluated risks. The purpose of this step is to modify the risk by applying controls and measures. The activities of managing, controlling, and remediating are the core functions of risk treatment, which can involve avoiding, reducing, sharing, or retaining the risk. The other options listed are distinct, preceding steps in the overall risk management process.

Why Incorrect

A. Risk avoidance is a specific strategy or option within the risk treatment step, not the entire process step itself.
B. Risk identification is the process of finding, recognizing, and describing risks, which occurs before any treatment action is taken.
C. Risk evaluation is the process of comparing risk analysis results with risk criteria to determine if treatment is necessary.

References

1. International Organization for Standardization. (2018). ISO 31000:2018 Risk management — Guidelines. Clause 6.5, "Risk treatment," states, "The purpose of risk treatment is to select and implement options for addressing risk." It further details the selection and implementation of these controls.

2. Purdy, G. (2010). ISO 31000:2009—Setting a New Standard for Risk Management. Risk Analysis: An International Journal, 30(6), 881-886. In the description of the risk management process (p. 883), risk treatment is explicitly defined as the stage where options for modifying risk are selected and implemented. https://doi.org/10.1111/j.1539-6924.2010.01442.x

3. University of Queensland. (2021). Enterprise Risk Management Framework. Section 4.3.4, "Risk Treatment," describes this step as involving the development and implementation of cost-effective strategies and action plans for managing risks. This aligns with the ISO 31000 standard on which the framework is based.