ISO-31000-Lead-Risk-Manager practice question 15 of 35
Uncertainty leads to a changing context
Full set: 100 questionsDomain Fundamental principles and concepts of risk management
The statement is correct. According to the principles and process outlined in ISO 31000, the context in which an organization operates is not static; it is dynamic and continually evolving. This evolution is fundamentally driven by uncertainty. Uncertainty, defined in ISO 31000 as a "state, even partial, of deficiency of information," relates to the potential for future events and their consequences. As new information becomes available or as uncertain events materialize, the organization's internal and external context changes. For example, uncertainty about future economic conditions, technological advancements, or regulatory shifts means the context is in a constant state of potential change. The risk management process must therefore be iterative, with continuous monitoring and review to detect and respond to these changes in context.
Stating this is "False" would imply that context is static or that changes to it are independent of uncertainty. This contradicts a core tenet of ISO 31000, which treats risk management as a dynamic and integral part of decision-making that must adapt to change. The entire purpose of the "Monitoring and review" step (Clause 6.7) in the risk management process is to systematically track risks and the effectiveness of controls in light of the evolving internal and external context, which changes precisely because of unfolding uncertainties.
1. International Organization for Standardization (ISO). (2018). ISO 31000:2018 Risk management — Guidelines.
Clause 6.7 (Monitoring and review): This clause states that the purpose of monitoring and review is to assure and improve the effectiveness of the risk management process. This is achieved
in part
by "detecting changes in the external and internal context... which can require revision of risk treatments and priorities." This directly links the need for monitoring to a changing context.
Clause 6.3.2 (Establishing the external context): This section lists factors such as the "social
cultural
political
legal
regulatory
financial
technological
economic
and environmental" environment. These factors are inherently uncertain and subject to change
thus making the context dynamic.
Principle (d) "Iterative": The standard lists "Iterative" as a key principle of risk management
stating that "Risk management is iterative. As new information becomes available
and as a result of monitoring and review
the understanding of risk can change. This leads to the re-analysis of risks
and the revision of risk treatments and controls." This new information directly addresses and alters the state of uncertainty
thereby changing the context.
2. Purdy
G. (2010). ISO 31000:2009—Setting a New Standard for Risk Management. Risk Analysis
30(6)
881-886.
Page 884
Section "Principles for Managing Risk": The author discusses the principle that risk management should be "dynamic
iterative and responsive to change." It explains
"Organizations exist in a context that changes. Risk management anticipates
detects
acknowledges and responds to those changes and events in an appropriate and timely manner." These "changes and events" are the materialization of uncertainties
which directly alter the context. (DOI: https://doi.org/10.1111/j.1539-6924.2010.01442.x)
3. Lalonde
C.
& Boiral
O. (2012). Managing risks through ISO 31000: A critical analysis. Risk Management
14(4)
272-300.
Page 280: The authors note that the ISO 31000 process begins with establishing the context
which "is not a static photograph of the organization and its environment
but a dynamic process that must be regularly updated." This dynamism is a direct consequence of the uncertainties inherent in the internal and external environments. (DOI: https://doi.org/10.1057/rm.2012.9)
Keep practicing
Take the free ISO-31000-Lead-Risk-Manager practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other ISO-31000-Lead-Risk-Manager practice questions
- Question 1New definition of risk under ISO 31000 and 31010 is:
- Question 2ISO uses the concept of uncertainty as the driver and rationale for risk management.
- Question 3Which type of risk remains after risk treatment has been applied?
- Question 4Risk management is tailored.
- Question 5Which of the following tools are used Risk managers for communication between stakeholder…
- Question 6means doing something according to a plan or method.