ISO-31000-Lead-Risk-Manager practice question 22 of 35
What does the probability of occurrence multiplied by the impact of the event, equals to
Full set: 100 questionsDomain Risk assessment
The formula Probability of occurrence × Impact of the event is a common technique in quantitative or semi-quantitative risk analysis. The product of these two variables yields a numerical value or score. This value represents the significance, size, or severity of the risk, which is most precisely termed its magnitude. While the term "level of risk" is also correct in a broader sense, "magnitude" specifically refers to the calculated value itself. The ISO 31000:2018 standard defines "level of risk" as the "magnitude of a risk... expressed in terms of the combination of consequences and their likelihood." This indicates that the calculation directly determines the magnitude.
A. Risk Tangent: This is not a recognized term within the ISO 31000 framework or standard risk management vocabulary. It appears to be a distractor option combining mathematical and risk terminology incorrectly.
B. Risk Scale: A risk scale is the measurement system used to rate the inputs (i.e., probability and impact), for example, on a scale of 1 to 5. It is the tool for measurement, not the result of the calculation.
C. Risk Level: Although closely related and often used synonymously with magnitude, "level" can also refer to the qualitative band (e.g., 'High', 'Medium', 'Low') into which the calculated magnitude falls. "Magnitude" is the more precise term for the specific numerical output of the formula. ---
1. ISO 31000:2018 - Risk management — Guidelines, Clause 3.8: The standard defines "level of risk" as the "magnitude of a risk or combination of risks, expressed in terms of the combination of consequences and their likelihood." This directly links the calculation (combination) to the concept of magnitude.
2. ISO Guide 73:2009 - Risk management — Vocabulary, Definition 3.6.1.8: This guide, which provides the foundational vocabulary for ISO 31000, offers the same definition: "level of risk: magnitude of a risk... expressed in terms of the combination of consequences... and their likelihood." The calculation's result is the expression of this magnitude.
3. Purdy, G. (2010). ISO 31000:2009—Setting a new standard for risk management. Risk Analysis: An International Journal, 30(6), 881-886. In section 4, the paper notes, "The level of risk (sometimes called risk magnitude) is determined by a combination of the consequences of an event and the associated likelihood of occurrence." This highlights the interchangeability but also the distinction, where magnitude is the core component. DOI: https://doi.org/10.1111/j.1539-6924.2010.01442.x
4. Aven, T. (2016). Risk assessment and risk management: Review of recent advances on their foundation. European Journal of Operational Research, 253(1), 1-13. This paper discusses various risk metrics, referring to the product of probability and consequence as a simplified measure used to represent the magnitude of a risk for comparison and ranking purposes. DOI: https://doi.org/10.1016/j.ejor.2015.12.023
Keep practicing
Take the free ISO-31000-Lead-Risk-Manager practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other ISO-31000-Lead-Risk-Manager practice questions
- Question 1New definition of risk under ISO 31000 and 31010 is:
- Question 2ISO uses the concept of uncertainty as the driver and rationale for risk management.
- Question 3Which type of risk remains after risk treatment has been applied?
- Question 4Risk management is tailored.
- Question 5Which of the following tools are used Risk managers for communication between stakeholder…
- Question 6means doing something according to a plan or method.