ISTQB-ATTA practice question 12 of 15
Select TWO solutions how the team could achieve significant benefits in the use of this tool within the next 6 months? (3 credits, for 1 out of 2 correct 1 credit) 3 credits [K4]
Full set: 65 questionsTo achieve significant benefits from test automation within a short timeframe (6 months), the team should focus on two key areas: strategy and technical implementation. Option D addresses the strategy by adopting a risk-based approach, concentrating automation efforts on critical system parts to maximize return on investment (ROI) and demonstrate value quickly. Option A addresses the technical implementation by introducing data-driven or keyword-driven techniques. These approaches improve the maintainability, reusability, and scalability of the test suite, reducing long-term effort and allowing for the creation of more tests with less code, which is a significant benefit.
B. Changing the entire development process is a major, long-term undertaking whose benefits would not be fully realized within the 6-month timeframe.
C. A test management tool improves organization and reporting but does not directly increase the efficiency, robustness, or coverage of the automation tool itself.
E. Involving business testers is a valuable goal, but it often requires significant upfront investment in training and framework adaptation, making it less likely to yield significant benefits within 6 months compared to A and D. ---
1. ISTQB Advanced Level Test Automation Engineer Syllabus (Version 2016)
Supporting Answer D: Section 2.3.1
"Test Automation Strategy
" emphasizes the importance of selecting which tests to automate. It states
"The test cases to be automated should be selected based on a cost/benefit analysis or on risk
" which directly supports the strategy of identifying and focusing on critical parts of the system.
Supporting Answer A: Section 4.2.2
"Design for Maintainability and Reusability
" explicitly discusses data-driven and keyword-driven approaches. It notes that these techniques "separate the test data from the test scripts" and "separate the test case design from the implementation details
" which are key to creating a maintainable and scalable solution that provides significant long-term benefits.
2. Fewster
M.
& Graham
D. (1999). Software Test Automation: Effective use of test execution tools. Addison-Wesley.
Supporting Answers A and D: Chapter 5
"Architecture
" details the principles of creating a robust test automation architecture
including data-driven techniques (p. 155). Chapter 7
"Metrics and Management
" discusses the importance of a pilot project to "prove the concept and to demonstrate the benefits" (p. 235)
which aligns with focusing on a critical area to show value.
3. Gao
J.
et al. (2003). A keyword-driven and data-driven framework for automated testing. In Proceedings of the 27th Annual International Computer Software and Applications Conference (COMPSAC'03). IEEE.
Supporting Answer A: This academic paper describes the benefits of keyword-driven and data-driven frameworks
stating they "improve the productivity of test-case authoring and the maintainability of test-ware" (Abstract). This directly supports the idea that introducing these techniques leads to significant benefits. DOI: 10.1109/CMPSAC.2003.1245351
Keep practicing
Take the free ISTQB-ATTA practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other ISTQB-ATTA practice questions
- Question 3Which additional set of test cases is needed to achieve both 100% statement coverage and …
- Question 4How many test cases are needed to test code fragment lines 26 – 32 to achieve 100% condit…
- Question 6It has been suggested to organize a performance test to find out more regarding the third…
- Question 7To address reliability a number of measures will be taken throughout the development and …
- Question 8A developer has spent three days looking at a system that crashes now and then. The probl…
- Question 9Based on the state diagram above, how many test cases are needed to achieve 1-switch cove…