To expand its operation, Steel Co. decides to build a new plant. Despite of excitement, the senior management is very concerned about the complexity…

Choose your answer, then check it against the explanation.

To expand its operation, Steel Co. decides to build a new plant. Despite of excitement, the senior management is very concerned about the complexity and risks of such project. Hugo, the procurement manager, suggests that the company can adopt a model form of contract. What is the advantage of using model form of contract?