L4M4 practice question 20 of 25
A buyer for a large manufacturing organisation is assessing a sole supplier tender opportunity. The buyer is finding it challenging to differentiate the proposals on unit purchase price. Are there any added values that the procurement manager can use to leverage the sole supplier proposal?
Full set: 293 questionsIn a sole supplier situation, while price leverage may be limited, a buyer is not without influence. The supplier still values the business relationship and revenue. The buyer can and should negotiate for non-price factors, often termed 'added value.' These can include improved after-sales service, better warranty terms, technical support, training, favourable payment terms, or innovation commitments. Focusing on the total cost of ownership (TCO) rather than just the unit price allows the buyer to create value and improve the overall commercial deal, even with a single available source.
A. Re-starting a tender is pointless if there is only one supplier capable of meeting the need.
B. A proactive buyer should never be passive and should always seek to negotiate and add value for the organisation.
C. A buyer always has some leverage, even if it's the option to not buy or to seek an alternative solution internally.
1. CIPS (2019). Commercial Negotiation, L4M3. Profex Publishing Limited. (Unit 3.2, 'Leverage in negotiation', discusses how to create leverage even in situations of low buyer power, such as single/sole source scenarios).
2. Monczka, R. M., Handfield, R. B., Giunipero, L. C., & Patterson, J. L. (2016). Purchasing and Supply Chain Management (6th ed.). Cengage Learning. (Chapter 15, 'Supplier Management and Development', covers negotiating with suppliers, including sole sources, for continuous improvement and value beyond price).
3. Shapiro, R. D., & Heskett, J. L. (1985). Logistics Strategy: Cases and Concepts. West Publishing Company. (The concept of Total Cost of Ownership (TCO) is explored, which is a key framework for identifying non-price value levers in negotiations, as cited in various procurement academic literature).
Keep practicing
Take the free L4M4 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other L4M4 practice questions
- Question 1What is the best way to prevent potential issues of conflicts of interest?
- Question 2Which of the following incoterms has the lowest risk to the buyer?
- Question 3What is a major benefit to using Incoterms when sourcing goods internationally?
- Question 4When using a 'credit account' payment mechanism, when does a supplier receive payment for…
- Question 5Which of the following are examples of secondary data? Select TWO
- Question 6A procurement manager has a new contract to award. They know there will be considerable i…