L5M2 practice question 10 of 25
Which of the following will you put into box 5?
Full set: 115 questionsThe diagram displays the Kraljic Matrix, which categorises procurement items based on their profit impact and supply risk. The arrow in box 5 points from the 'Bottleneck' quadrant (low profit impact, high supply risk) to the 'Non-critical' quadrant (low profit impact, low supply risk). This movement represents a strategic action to reduce the supply risk of an item. Introducing new technology is a primary method to achieve this. For instance, new manufacturing processes (like 3D printing) or material sciences can allow a company to redesign a product, replacing a unique, high-risk component with a standardised, easily sourced one. This fundamentally reduces dependency on a limited supply base, thereby lowering supply risk and moving the item to the non-critical category.
B. forward contract: This is a financial tool to manage price volatility risk, not the underlying supply availability risk that characterises bottleneck items.
C. outsource: Outsourcing is a sourcing strategy. For a bottleneck item, it might increase dependency and risk rather than reduce it, unless it's part of a broader redesign.
D. insurance: This is a risk transference strategy that provides financial compensation for a loss but does not reduce the actual likelihood or nature of the supply disruption itself.
1. Kraljic
P. (1983). Purchasing must become supply management. Harvard Business Review
61(5)
pp. 109-117. (In his seminal article
Kraljic discusses strategies for bottleneck items which include reducing dependence through actions like searching for new materials or vendors
which is often enabled by new technology).
2. van Weele
A. J. (2018). Purchasing and Supply Chain Management. 7th ed. Cengage. (Chapter 5 on Purchasing Portfolio Management details strategies for bottleneck items
including accepting dependence and reducing it through tactics like developing alternative products or suppliers
which aligns with technological innovation).
3. CIPS (Chartered Institute of Procurement & Supply). (2018). Managing Supply Chain Risk (L5M2). Stamford
UK: Profex Publishing. (The official CIPS study guide explains that for bottleneck items
a key strategy is to reduce risk by redesigning products to use more standard components
an action often facilitated by technological advancements).
Keep practicing
Take the free L5M2 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other L5M2 practice questions
- Question 1Which of the following is a component of the Sarbanes-Oxley Regulations?
- Question 2Oliver is a procurement manager and he is trying to work out the likelihood that a suppli…
- Question 3Which of the following will you put into box 6?
- Question 4Which of the following FIDIC Contracts would be suitable for a contract for offshore wind…
- Question 5ISO 31000 is built on 11 guiding principles. Identify THREE of these.
- Question 6The USA Foreign Corrupt Practices Act (FCPA) is further reaching than the UK's Bribery Ac…