LEED-AP-OM practice question 15 of 25
A district energy system provides chilled and hot water to a building on a campus. What equipment must be commissioned to meet the requirements of Energy and Atmosphere Credit, Existing Building Commissioning - Analysis, Option 1. Existing Building Commissioning?
Full set: 168 questionsThe Energy and Atmosphere Credit, Existing Building Commissioning - Analysis, Option 1 in LEED AP O+M V4.1 requires the commissioning of major energy-using systems1. In a district energy system that provides chilled and hot water to a building, the heat exchangers play a crucial role in transferring heat between the hot and chilled water circuits. Therefore, to meet the requirements of this credit, the heat exchangers must be commissioned to ensure they are operating efficiently and effectively1.
Reference: LEED AP O+M Exam, USGBC Guide, Lawrence Berkeley National Laboratory, Department of Energy.
Keep practicing
Take the free LEED-AP-OM practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other LEED-AP-OM practice questions
- Question 1For an office building with few visitors, which of the following actions must the project…
- Question 2Which of the following is the most appropriate use of untreated stormwater?
- Question 3How is the energy baseline determined in Minimum Energy Performance if the building type …
- Question 4An ASHRAE Level 1 walkthrough analysis contributes to what prerequisite or credit?
- Question 5Under Indoor Environmental Quality Credit, Interior Lighting, outlet powered task lightin…
- Question 6A 1,500 ft2 (139 m2) mobile home is built in the downtown area of a major city. 90% of th…