NCS-CORE practice question 35 of 35
A customer has engaged a Nutanix consultant to deploy a cluster consisting of two NX-3460-G6 blocks. The consultant arrives at the customer site and fines the following: * One rack with a total of 5U available * Two ToR switches with 14 total available ports * Dual PDUs with six available sockets What will prevent the consultant from successfully installing the cluster?
Full set: 302 questionsAn NX-3460-G6 is a 2U, 4-node block. Two blocks require 8 nodes. For basic redundant connectivity, each node requires two data ports (e.g., 10/25 GbE) and one IPMI port. This totals 3 ports per node, or 24 ports for the 8-node cluster (8 nodes 3 ports/node). With only 14 ports available, there is a significant shortfall that will prevent a successful installation. Additionally, while the total 5U of rack space is technically sufficient for two 2U blocks (4U total), if the space is not contiguous (e.g., 3U in one location, 2U in another), it would also prevent the installation of a 2U block.
A. Power is sufficient (4 PSUs need 4 sockets; 6 are available). The rack space continuity is a potential issue, but the network port deficit is a definite blocker.
B. Rack space is sufficient (4U needed, 5U available). Power sockets are also sufficient. This option incorrectly identifies both constraints.
C. This option correctly identifies the network port issue but incorrectly states there are insufficient power sockets.
D. This option is identical to C, correctly identifying the network port issue but incorrectly stating there are insufficient power sockets.
1. Nutanix Hardware Platform Documentation, NX-3460-G6 Specifications. (Confirms 2U chassis and 4 nodes per block).
2. Nutanix Physical Networking Best Practices Guide, "Port Requirements" section. (Details the requirement for redundant data ports and a dedicated IPMI port per node).
Keep practicing
Take the free NCS-CORE practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other NCS-CORE practice questions
- Question 1In a 20-node ESXi deployment, the customer needs additional resiliency to survive the los…
- Question 2A consultant is planning a new cluster installation and needs to locate the Shared IPMI p…
- Question 3Which configuration item is a hard requirement to deploy a Nutanix cluster?
- Question 4A customer is running out of storage in an ESXi cluster. The customer wants to add storag…
- Question 5A consultant configures a Nutanix cluster and integrates the hosts into vCenter using VMw…
- Question 6An administrator wants to utilize Network Visualization to monitor the physical and logic…