NCSC-LEVEL-1 practice question 3 of 15

While preparing for a new four-node cluster installation, the consultant has a Tech Review Call with the customer. The hardware is as follows: * 4…

Choose your answer, then check it against the explanation.

While preparing for a new four-node cluster installation, the consultant has a Tech Review Call with the customer. The hardware is as follows: * 4 nodes in 1 Block * 8 x 10 GbE Ports * 4 x 1 GbE IPMI Ports * Adequate Ethernet ports are available * Ethernet cables are correct and available * Adequate rack space is available Which remaining item must be confirmed as available onsite?