NCSC-LEVEL-1 practice question 3 of 15

While preparing for a new four-node cluster installation, the consultant has a Tech Review Call with the customer. The hardware is as follows: * 4 nodes in 1 Block * 8 x 10 GbE Ports * 4 x 1 GbE IPMI Ports * Adequate Ethernet ports are available * Ethernet cables are correct and available * Adequate rack space is available Which remaining item must be confirmed as available onsite?

Full set: 78 questions
Answer options
A: Crash Cart
B: Fibre Channel switches
C: Redundant 208v power Correct answer
D: Redundant 110v power
Correct Answer:
C. Redundant 208v power