Which of the following COBIT and NIST implementation steps may be reversed depending on the culture of the organization?
Full set: 50 questionsCorrect Answer:
C. Step 1: Prioritize and Scope and Step 2: Orient
Explanation
According to the ISACA guide, the order of these two steps may be reversed depending on the culture of the organization and the level of stakeholder engagement1. Some organizations may prefer to start with a broad orientation of the NIST CSF and COBIT 2019 before scoping and prioritizing the implementation, while others may want to define the scope and priorities first and then orient the stakeholders accordingly. Reference Implementing the NIST Cybersecurity Framework Using COBIT 2019, page 17.
Keep practicing
Take the free NIST-COBIT-2019 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other NIST-COBIT-2019 practice questions
- Question 1How should gaps identified between the current and target profiles be addressed?
- Question 2Combining CSF principles with COBIT 2019 practices helps to ensure value, manage risk, an…
- Question 3What does a CSF Informative Reference within the CSF Core provide?
- Question 4Which of the following COBIT tasks and activities corresponds to CSF Step 1: Prioritize a…
- Question 6The CSF Implementation Tiers distinguish three fundamental dimensions of risk management …
- Question 7During CSF life cycle action plan review, which of the following tasks is associated with…