OGA-031 practice question 6 of 15

What Implementation and Migration element can be used to model sub-projects or tasks within a project, complete projects, programs, or project portfolios?

Full set: 78 questions
Answer options
A: Project component
B: Work package Correct answer
C: Plateau
D: Implementation event
Correct Answer:
B. Work package
Explanation

A Work Package is the standard ArchiMate element within the Implementation and Migration Layer used to model a defined set of actions to achieve a specific goal. Its definition explicitly states that it can represent various levels of project granularity, including tasks, sub-projects, entire projects, or even programs and portfolios. This makes it the correct element for modeling the described scope of work.

Why Incorrect

A. "Project component" is not a standard element in the ArchiMate 3.1 specification.
C. A Plateau represents a stable state of the architecture at a specific point in time, not a package of work or a project.
D. An Implementation Event represents a point in time or a state change during a migration, not a collection of tasks or a project.

References

- The ArchiMate® 3.1 Specification, C197, Section 12.2.2, Work Package. The definition states: "A work package can be used to model sub-projects or tasks within a project, complete projects, programs, or project portfolios."

- The ArchiMate® 3.1 Specification, C197, Figure 89: Implementation and Migration Metamodel. Shows the Work Package element and its relationships.