OGEA-101 practice question 23 of 25
What is defined as the effect of uncertainty on objectives?
Full set: 162 questionsDomain ADM Techniques
The term "Risk" is formally defined as "the effect of uncertainty on objectives." This definition is adopted by The Open Group in the TOGAF® Standard directly from the international standard for risk management, ISO 31000:2018. It signifies that any uncertainty, whether its potential outcome is positive or negative, can impact the achievement of an organization's goals. In the context of enterprise architecture, this involves identifying and managing uncertainties that could affect the objectives of the architecture work or the enterprise itself.
A. Vulnerability: A vulnerability is a weakness or flaw in an asset or control that can be exploited by one or more threats.
C. Continuity: Continuity, often in the context of Business Continuity, is the capability to maintain essential functions during and after a disaster has occurred.
D. Threat: A threat is a potential cause of an unwanted incident, which may result in harm to a system or organization.
1. The TOGAF® Standard, 10th Edition, Part I, Chapter 3: Definitions, Section 3.73. The standard explicitly defines Risk as: "The effect of uncertainty on objectives. Note: This definition is taken from ISO 31000:2018."
2. ISO 31000:2018, Risk management — Guidelines, Clause 3.1. This international standard provides the foundational definition of risk as the "effect of uncertainty on objectives."
3. The Open Group, O-RA-21, Open FAIR™ Risk Analysis Body of Knowledge, Version 2.0.1, Section 1.2. While focusing on FAIR, it aligns with the standard ISO 31000 definition of risk as a foundational concept.
Keep practicing
Take the free OGEA-101 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other OGEA-101 practice questions
- Question 1Which of the following statements about architecture partitioning are correct*? 1 Partiti…
- Question 2Which of the following describes how the Enterprise Continuum is used when developing an …
- Question 4What ensures that a project transitioning into implementation also smoothly transitions i…
- Question 5What is an objective of the ADM Preliminary Phase?
- Question 6Which section of the TOGAF template for Architecture Principles should highlight the requ…
- Question 7Which of the following are the four purposes that typically frame the planning horizon, d…