PCCSE practice question 33 of 35

Which options show the steps required to upgrade Console when using projects?

Full set: 259 questions
Answer options
A: Upgrade all Supervisor Consoles Upgrade Central Console Correct answer
B: Upgrade Central Console Upgrade Central Console Defenders
C: Upgrade Defender Upgrade Central Console Upgrade Supervisor Consoles
D: Upgrade Central Console Upgrade all Supervisor Consoles
Correct Answer:
A. Upgrade all Supervisor Consoles Upgrade Central Console
Explanation

In a Prisma Cloud multi-console deployment (Central Console with Projects/Supervisors), the upgrade process must follow a specific order to maintain compatibility and control. All Supervisor Consoles must be upgraded first. Once all Supervisors are running the new version, the Central Console can be upgraded. This bottom-up approach ensures that the managed consoles are ready to communicate with the upgraded central management plane.

Why Incorrect

B. Upgrading the Central Console first is the incorrect order and can cause communication failures with older Supervisor versions.
C. The upgrade order is incorrect. Defenders are upgraded after the Console, and the Central Console is upgraded after the Supervisors.
D. This represents the reverse of the correct upgrade order. Upgrading the Central Console before the Supervisors is not the supported procedure.

References

1. Palo Alto Networks, Prisma Cloud Administrator's Guide (Self-Hosted), "Upgrade a multi-Console deployment". The guide states, "In a multi-Console deployment, where a Central Console manages one or more Supervisor Consoles, you must upgrade all Supervisor Consoles before upgrading the Central Console."