PDD practice question 31 of 35

Before construction documents are complete, the owner requests a review of the timeline allowed for ASIs, RFIs, RFPs, and change orders as defined in the project manual. Which section of the project manual is relevant to this request?

Full set: 100 questions
Answer options
A: AIA Document A201
B: Supplementary Conditions
C: Section 01 26 00 Contract Modification Procedures
D: Section 01 35 16 Alteration Project Procedures
Correct Answer:
C