For which of the following reasons is sheet piling used? (Check the three that apply)

Full set: 100 questions
Answer options
A: A grade beam needs support.
B: Raked shoring should be created.
C: A pile cap needs support.
D: An excessive slope on the sides of the excavation would be required.
E: The soil surrounding an excavation site will not support itself during or after the digging.
F: The excavation adjoins a property line and the adjacent property cannot be disturbed.
Correct Answer:
D, E, F