PeopleCert certification practice

Free PRINCE2-AGILE-PRACTITIONER Practice Test

10 free PRINCE2-AGILE-PRACTITIONER exam-style questions for PRINCE2 Agile Practitioner Project Management, with answers, explanations and source references.

Last updated

Full set: 50 questions
Project scenario - Get fit with football! (Note: The companies and people within the scenario are fictional) Introduction A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres. Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support. This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited. Scope The initial scope of the project includes: a marketing campaign to promote the event; PeopleCert PRINCE2 Agile Practitioner question a celebrity to open the event; PeopleCert PRINCE2 Agile Practitioner question a website to provide information about the event and handle applications; PeopleCert PRINCE2 Agile Practitioner question an event village to support the 'family day out'; PeopleCert PRINCE2 Agile Practitioner question the training of LGA staff as volunteers to run and support the event; PeopleCert PRINCE2 Agile Practitioner question back-office processes to handle the applications; PeopleCert PRINCE2 Agile Practitioner question fundraising to cover the cost of the event. PeopleCert PRINCE2 Agile Practitioner question The project has been set up with four work streams to deliver this work: 1. Marketing 2. Website 3. Event Village 4. Staff Training Project Background The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'. Timeline An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes. PeopleCert PRINCE2 Agile Practitioner question Website - Additional information A new website will be built for the event. There are five work packages within this product: 1. Initial homepage: Website showing the event details, competition rules, etc. PeopleCert PRINCE2 Agile Practitioner question 2. Team Registration functionality: team name, player's names and ages; PeopleCert PRINCE2 Agile Practitioner question contact information; PeopleCert PRINCE2 Agile Practitioner question payment; PeopleCert PRINCE2 Agile Practitioner question lunch pack requirements (includes any special dietary needs); PeopleCert PRINCE2 Agile Practitioner question car parking requirements. PeopleCert PRINCE2 Agile Practitioner question 3. Social media promoting the event and its aims. 4. Applications (apps) to promote healthy lifestyles including fitness and healthy eating apps. 5. Health Park: An online knowledge base about healthy lifestyles that includes a discussion forum. PeopleCert PRINCE2 Agile Practitioner question The Website Team have a lot of experience in IT and have been using agile for several years. They are delivering the website through five two-week timeboxes. The team uses a Scrum Master to facilitate and the Scrum process and coach people accordingly. The Website Team are very good at Scrum. They have created a set of tasks to assess more difficult work and they refer to this as sprint zero. Using the Project Scenario and Website Additional information, answer the following question: There are several work packages being delivered during Stage 4. The Website Team Scrum Master is concerned that project-level issues may be overlooked and this might impact the Website Team during the current timebox. Which agile way of working can be used as part of the 'controlling a stage' process to ensure that these issues are identified?
Answer options
Project scenario - Get fit with football! (Note: The companies and people within the scenario are fictional) Introduction A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres. Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support. This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited. Scope The initial scope of the project includes: a marketing campaign to promote the event; PeopleCert PRINCE2 Agile Practitioner question a celebrity to open the event; PeopleCert PRINCE2 Agile Practitioner question a website to provide information about the event and handle applications; PeopleCert PRINCE2 Agile Practitioner question an event village to support the 'family day out'; PeopleCert PRINCE2 Agile Practitioner question the training of LGA staff as volunteers to run and support the event; PeopleCert PRINCE2 Agile Practitioner question back-office processes to handle the applications; PeopleCert PRINCE2 Agile Practitioner question fundraising to cover the cost of the event. PeopleCert PRINCE2 Agile Practitioner question The project has been set up with four work streams to deliver this work: 1. Marketing 2. Website 3. Event Village 4. Staff Training Project Background The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'. Timeline An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes. PeopleCert PRINCE2 Agile Practitioner question Marketing - Additional information The marketing campaign has two key areas to promote: 1. The event itself including the football tournament, event village and fundraising activities. 2. The LGA's long term aim to improve the fitness of children under the age of 16. The Marketing Team has received some initial Scrum training but is unsure how it can be applied to their marketing work. The Marketing Team is keen that the project manager provides them with a clear brief for the campaign before they spend too much time on it. They have experience of working with a variety of marketing channels, although they are not sure which channel(s) will work most effectively to promote this type of event, and in particular to promote the LGA's longer term health aims. The Marketing Team is not clear on the priority to assign to the two aims for the event. The Marketing Team will publish advertisements and/or promotional material every week, with more information in each issue to keep the message up to date. Nine releases are scheduled at the end of each of the nine week-long timeboxes. The nine timeboxes within the marketing work stream are scheduled to include: advertisements: PeopleCert PRINCE2 Agile Practitioner question a radio interview; PeopleCert PRINCE2 Agile Practitioner question production of a hand-out/flyer; PeopleCert PRINCE2 Agile Practitioner question banners and signs to put up around the town and at the event; PeopleCert PRINCE2 Agile Practitioner question the provision of a website and social media content; PeopleCert PRINCE2 Agile Practitioner question promotional posters to be displayed by local businesses. PeopleCert PRINCE2 Agile Practitioner question Using the Project Scenario and Marketing Additional information, answer the following question: The project manager recommends that Stage 2 should be broken down further with more stage boundaries linked to the weekly publication of a newspaper advertisement. Using the Timeline, which statement BEST evaluates this proposal in relation to the 'manage by stages' principle?
Answer options
Project scenario - Get fit with football! (Note: The companies and people within the scenario are fictional) Introduction A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres. Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support. This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited. Scope The initial scope of the project includes: a marketing campaign to promote the event; PeopleCert PRINCE2 Agile Practitioner question a celebrity to open the event; PeopleCert PRINCE2 Agile Practitioner question a website to provide information about the event and handle applications; PeopleCert PRINCE2 Agile Practitioner question an event village to support the 'family day out'; PeopleCert PRINCE2 Agile Practitioner question the training of LGA staff as volunteers to run and support the event; PeopleCert PRINCE2 Agile Practitioner question back-office processes to handle the applications; PeopleCert PRINCE2 Agile Practitioner question fundraising to cover the cost of the event. PeopleCert PRINCE2 Agile Practitioner question The project has been set up with four work streams to deliver this work: 1. Marketing 2. Website 3. Event Village 4. Staff Training Project Background The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'. Timeline An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes. PeopleCert PRINCE2 Agile Practitioner question Website - Additional information A new website will be built for the event. There are five work packages within this product: 1. Initial homepage: Website showing the event details, competition rules, etc. PeopleCert PRINCE2 Agile Practitioner question 2. Team Registration functionality: team name, player's names and ages; PeopleCert PRINCE2 Agile Practitioner question contact information; PeopleCert PRINCE2 Agile Practitioner question payment; PeopleCert PRINCE2 Agile Practitioner question lunch pack requirements (includes any special dietary needs); PeopleCert PRINCE2 Agile Practitioner question car parking requirements. PeopleCert PRINCE2 Agile Practitioner question 3. Social media promoting the event and its aims. 4. Applications (apps) to promote healthy lifestyles including fitness and healthy eating apps. 5. Health Park: An online knowledge base about healthy lifestyles that includes a discussion forum. PeopleCert PRINCE2 Agile Practitioner question The Website Team have a lot of experience in IT and have been using agile for several years. They are delivering the website through five two-week timeboxes. The team uses a Scrum Master to facilitate and the Scrum process and coach people accordingly. The Website Team are very good at Scrum. They have created a set of tasks to assess more difficult work and they refer to this as sprint zero. Using the Project Scenario and Website Additional information, answer the following question: During the 'initiating a project' process, the project manager has decided to use the Cynefin framework to assess the project. As a result, the following observation was made as part of the assessment: 'There is a relationship between the social media websites promoting active lifestyles and participation in sport. This in turn leads to an increase in the health and fitness of the people. It will not be possible to measure the effect of the social media websites until after the project. The results of early communications on the websites should be reviewed in order to identify what effect it may be having, and why. This will then feed into further longer term initiatives at the LGA.' How should this relationship be assessed according to the Cynefin framework?
Answer options
Project scenario - Get fit with football! (Note: The companies and people within the scenario are fictional) Introduction A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres. Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support. This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited. Scope The initial scope of the project includes: a marketing campaign to promote the event; PeopleCert PRINCE2 Agile Practitioner question a celebrity to open the event; PeopleCert PRINCE2 Agile Practitioner question a website to provide information about the event and handle applications; PeopleCert PRINCE2 Agile Practitioner question an event village to support the 'family day out'; PeopleCert PRINCE2 Agile Practitioner question the training of LGA staff as volunteers to run and support the event; PeopleCert PRINCE2 Agile Practitioner question back-office processes to handle the applications; PeopleCert PRINCE2 Agile Practitioner question fundraising to cover the cost of the event. PeopleCert PRINCE2 Agile Practitioner question The project has been set up with four work streams to deliver this work: 1. Marketing 2. Website 3. Event Village 4. Staff Training Project Background The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'. Timeline An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes. PeopleCert PRINCE2 Agile Practitioner question Event Village - Additional information The aim of the event village is to provide a range of services and activities for anyone attending the football tournament. The event village will comprise a number of work packages: 1. Event village design 2. A 'kids-zone' which includes trampolines and swings, as well as the opportunity to try out other sporting activities 3. Stalls which will be sold to local businesses to raise funds for the event: Refreshment stalls within a large food tent. The LGA is keen to promote the culinary diversity of the PeopleCert PRINCE2 Agile Practitioner question town whilst adhering to the objective of eating healthily. There are 30 vendor stalls selling products related to the event. PeopleCert PRINCE2 Agile Practitioner question The LGA has five stalls to promote their longer term aims and to demonstrate current and future PeopleCert PRINCE2 Agile Practitioner question initiatives. 4. A car park for 200 cars. 5. Temporary facilities including changing rooms, toilets and shower facilities. 6. Dismantling of the event village and clean up. The Event Village Team is assembled using staff from various LGA departments who have no experience of working with agile. Using the Project Scenario and Event Village Additional information, answer the following question: All public events supported by the LGA must be fully accessible to all visitors. How should this requirement be recorded?
Answer options
Project scenario - Get fit with football! (Note: The companies and people within the scenario are fictional) Introduction A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres. Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support. This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited. Scope The initial scope of the project includes: a marketing campaign to promote the event; PeopleCert PRINCE2 Agile Practitioner question a celebrity to open the event; PeopleCert PRINCE2 Agile Practitioner question a website to provide information about the event and handle applications; PeopleCert PRINCE2 Agile Practitioner question an event village to support the 'family day out'; PeopleCert PRINCE2 Agile Practitioner question the training of LGA staff as volunteers to run and support the event; PeopleCert PRINCE2 Agile Practitioner question back-office processes to handle the applications; PeopleCert PRINCE2 Agile Practitioner question fundraising to cover the cost of the event. PeopleCert PRINCE2 Agile Practitioner question The project has been set up with four work streams to deliver this work: 1. Marketing 2. Website 3. Event Village 4. Staff Training Project Background The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'. Timeline An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes. PeopleCert PRINCE2 Agile Practitioner question Event Village - Additional information The aim of the event village is to provide a range of services and activities for anyone attending the football tournament. The event village will comprise a number of work packages: 1. Event village design 2. A 'kids-zone' which includes trampolines and swings, as well as the opportunity to try out other sporting activities 3. Stalls which will be sold to local businesses to raise funds for the event: Refreshment stalls within a large food tent. The LGA is keen to promote the culinary diversity of the PeopleCert PRINCE2 Agile Practitioner question town whilst adhering to the objective of eating healthily. There are 30 vendor stalls selling products related to the event. PeopleCert PRINCE2 Agile Practitioner question The LGA has five stalls to promote their longer term aims and to demonstrate current and future PeopleCert PRINCE2 Agile Practitioner question initiatives. 4. A car park for 200 cars. 5. Temporary facilities including changing rooms, toilets and shower facilities. 6. Dismantling of the event village and clean up. The Event Village Team is assembled using staff from various LGA departments who have no experience of working with agile. Using the Project Scenario and Event Village Additional information, answer the following question: A requirement for the changing room facilities in the Event Village has been defined as a technical story as follows: 'Changing room facilities should have water pressure between 1.5 - 3 bar and must have a water pressure of at least between 0.1 - 0.5 bar.' Has this requirement been recorded correctly?
Answer options
Project scenario - Get fit with football! (Note: The companies and people within the scenario are fictional) Introduction A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres. Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support. This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited. Scope The initial scope of the project includes: a marketing campaign to promote the event; PeopleCert PRINCE2 Agile Practitioner question a celebrity to open the event; PeopleCert PRINCE2 Agile Practitioner question a website to provide information about the event and handle applications; PeopleCert PRINCE2 Agile Practitioner question an event village to support the 'family day out'; PeopleCert PRINCE2 Agile Practitioner question the training of LGA staff as volunteers to run and support the event; PeopleCert PRINCE2 Agile Practitioner question back-office processes to handle the applications; PeopleCert PRINCE2 Agile Practitioner question fundraising to cover the cost of the event. PeopleCert PRINCE2 Agile Practitioner question The project has been set up with four work streams to deliver this work: 1. Marketing 2. Website 3. Event Village 4. Staff Training Project Background The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'. Timeline An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes. PeopleCert PRINCE2 Agile Practitioner question Staff Training - Additional information The event will be supervised primarily by LGA staff volunteers. They will need to be trained in various skills so that: A . the event is carried out safely and professionally; B . staff members are able to give advice on health and fitness. This is covered by four work packages: 1. Training syllabus: • High-level design of the manual. • Content of each module. 2. Course content for safety and professionalism: • Detailed design of two modules: • Health and Safety including basic first aid. • Customer relations to look after people attending the event. • Piloting the modules with a group of volunteers. 3. Course content tor giving advice on health and fitness: • Detailed design of two modules: • Exercise fundamentals including how to warm up and cool down. • Healthy eating including what types of food are good for you. • Piloting the modules with a group of volunteers. 4. Training delivery: • Production of the training manual; • Delivery of the training to the rest of the volunteers. The Staff Training Team is staffed by in-house training staff members that have been involved in several waterfall projects but have not had any exposure to agile. Using the Project Scenario and Staff Training Additional information, answer the following question: The Staff Training Team has developed the following user stories: • 'As a volunteer, I want to be trained in healthy eating so that I can answer questions from the public on the long term aims of the LGA during the football tournament.' - Should Have • As the LGA. I want all volunteers to have received mandatory health and safety training so that we can ensure that the event takes place in a safe environment for the public.' - Must Have A suitably qualified trainer has been scheduled to deliver a course covering both requirements. Unfortunately, there is no-one available from the LGA to quality check the course materials for the healthy eating training until three days after the date scheduled for training delivery. How should the team respond to this situation?
Answer options
Which is a reason for 'blending and weaving' PRINCE2 with agile at all levels within a project?
Answer options
Project scenario - Get fit with football! (Note: The companies and people within the scenario are fictional) Introduction A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres. Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support. This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited. Scope The initial scope of the project includes: a marketing campaign to promote the event; PeopleCert PRINCE2 Agile Practitioner question a celebrity to open the event; PeopleCert PRINCE2 Agile Practitioner question a website to provide information about the event and handle applications; PeopleCert PRINCE2 Agile Practitioner question an event village to support the 'family day out'; PeopleCert PRINCE2 Agile Practitioner question the training of LGA staff as volunteers to run and support the event; PeopleCert PRINCE2 Agile Practitioner question back-office processes to handle the applications; PeopleCert PRINCE2 Agile Practitioner question fundraising to cover the cost of the event. PeopleCert PRINCE2 Agile Practitioner question The project has been set up with four work streams to deliver this work: 1. Marketing 2. Website 3. Event Village 4. Staff Training Project Background The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'. Timeline An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes. PeopleCert PRINCE2 Agile Practitioner question Event Village - Additional information The aim of the event village is to provide a range of services and activities for anyone attending the football tournament. The event village will comprise a number of work packages: 1. Event village design 2. A 'kids-zone' which includes trampolines and swings, as well as the opportunity to try out other sporting activities 3. Stalls which will be sold to local businesses to raise funds for the event: Refreshment stalls within a large food tent. The LGA is keen to promote the culinary diversity of the PeopleCert PRINCE2 Agile Practitioner question town whilst adhering to the objective of eating healthily. There are 30 vendor stalls selling products related to the event. PeopleCert PRINCE2 Agile Practitioner question The LGA has five stalls to promote their longer term aims and to demonstrate current and future PeopleCert PRINCE2 Agile Practitioner question initiatives. 4. A car park for 200 cars. 5. Temporary facilities including changing rooms, toilets and shower facilities. 6. Dismantling of the event village and clean up. The Event Village Team is assembled using staff from various LGA departments who have no experience of working with agile. Using the Project Scenario and Event Village Additional information, answer the following question: A local newspaper has reported the results of a survey. The survey indicated that local residents are concerned that costs from the event may be incurred by local tax payers. Which action would have helped to avoid this situation?
Answer options
Project scenario - Get fit with football! (Note: The companies and people within the scenario are fictional) Introduction A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres. Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support. This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited. Scope The initial scope of the project includes: a marketing campaign to promote the event; PeopleCert PRINCE2 Agile Practitioner question a celebrity to open the event; PeopleCert PRINCE2 Agile Practitioner question a website to provide information about the event and handle applications; PeopleCert PRINCE2 Agile Practitioner question an event village to support the 'family day out'; PeopleCert PRINCE2 Agile Practitioner question the training of LGA staff as volunteers to run and support the event; PeopleCert PRINCE2 Agile Practitioner question back-office processes to handle the applications; PeopleCert PRINCE2 Agile Practitioner question fundraising to cover the cost of the event. PeopleCert PRINCE2 Agile Practitioner question The project has been set up with four work streams to deliver this work: 1. Marketing 2. Website 3. Event Village 4. Staff Training Project Background The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'. Timeline An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes. PeopleCert PRINCE2 Agile Practitioner question Staff Training - Additional information The event will be supervised primarily by LGA staff volunteers. They will need to be trained in various skills so that: A . the event is carried out safely and professionally; B . staff members are able to give advice on health and fitness. This is covered by four work packages: 1. Training syllabus: • High-level design of the manual. • Content of each module. 2. Course content for safety and professionalism: • Detailed design of two modules: • Health and Safety including basic first aid. • Customer relations to look after people attending the event. • Piloting the modules with a group of volunteers. 3. Course content tor giving advice on health and fitness: • Detailed design of two modules: • Exercise fundamentals including how to warm up and cool down. • Healthy eating including what types of food are good for you. • Piloting the modules with a group of volunteers. 4. Training delivery: • Production of the training manual; • Delivery of the training to the rest of the volunteers. The Staff Training Team is staffed by in-house training staff members that have been involved in several waterfall projects but have not had any exposure to agile. Using the Project Scenario and Staff Training Additional information, answer the following question: The Staff Training Team had been working to the following assumption: 'All volunteers will be trained in all training materials.' Quite late in the project, it has been identified that this assumption is incorrect. As a result, the team manager produced a chart of who needs to be trained in what modules. This was agreed with a customer representative and the team manager made the necessary amendments to the requirements in the backlog within the current timebox. What BEST explains why the team manager's approach complies with the 'embrace change' target?
Answer options
Project scenario - Get fit with football! (Note: The companies and people within the scenario are fictional) Introduction A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres. Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support. This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited. Scope The initial scope of the project includes: a marketing campaign to promote the event; PeopleCert PRINCE2 Agile Practitioner question a celebrity to open the event; PeopleCert PRINCE2 Agile Practitioner question a website to provide information about the event and handle applications; PeopleCert PRINCE2 Agile Practitioner question an event village to support the 'family day out'; PeopleCert PRINCE2 Agile Practitioner question the training of LGA staff as volunteers to run and support the event; PeopleCert PRINCE2 Agile Practitioner question back-office processes to handle the applications; PeopleCert PRINCE2 Agile Practitioner question fundraising to cover the cost of the event. PeopleCert PRINCE2 Agile Practitioner question The project has been set up with four work streams to deliver this work: 1. Marketing 2. Website 3. Event Village 4. Staff Training Project Background The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'. Timeline An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes. PeopleCert PRINCE2 Agile Practitioner question Website - Additional information A new website will be built for the event. There are five work packages within this product: 1. Initial homepage: Website showing the event details, competition rules, etc. PeopleCert PRINCE2 Agile Practitioner question 2. Team Registration functionality: team name, player's names and ages; PeopleCert PRINCE2 Agile Practitioner question contact information; PeopleCert PRINCE2 Agile Practitioner question payment; PeopleCert PRINCE2 Agile Practitioner question lunch pack requirements (includes any special dietary needs); PeopleCert PRINCE2 Agile Practitioner question car parking requirements. PeopleCert PRINCE2 Agile Practitioner question 3. Social media promoting the event and its aims. 4. Applications (apps) to promote healthy lifestyles including fitness and healthy eating apps. 5. Health Park: An online knowledge base about healthy lifestyles that includes a discussion forum. PeopleCert PRINCE2 Agile Practitioner question The Website Team have a lot of experience in IT and have been using agile for several years. They are delivering the website through five two-week timeboxes. The team uses a Scrum Master to facilitate and the Scrum process and coach people accordingly. The Website Team are very good at Scrum. They have created a set of tasks to assess more difficult work and they refer to this as sprint zero. Using the Project Scenario and Website Additional information, answer the following question: The Scrum Master has been advised by the supplier subject matter expert that the five day task of building the social media website is now almost complete - there is just one more day's work to do. How should this be shown on the burn-down chart?
Answer options
Question 1 of 10
Browse PeopleCert exams

Source context

How this practice set is maintained

Maintained by the CertMage content team, this page loads questions from the exam dataset connected to its preparation resource. When an answer includes a supporting reference, it is shown with that answer so you can review the underlying vendor documentation.

Certification objectives, interfaces, and vendor services can change. Verify important details against the provider's current exam guide and documentation before your exam.

Scroll to Top