Which is one of the six aspects of project performance to be managed?
Full set: 478 questionsPRINCE2 defines six aspects of project performance that must be managed to ensure the project is successful. These are costs, timescales, quality, scope, sustainability, and benefits. Tolerances are set for each of these aspects to enable management by exception. 'Timescales' is one of these six core performance metrics, focusing on whether the project is on schedule to meet its deadlines. The project manager monitors performance against these targets and escalates any forecast deviation beyond tolerance.
A. Efficiency: This is a general business metric and a potential benefit, but not one of the six specific performance aspects defined by PRINCE2.
C. Estimate: Estimates are used to forecast performance (e.g., cost and time), but 'estimate' itself is not a performance aspect to be managed.
D. Work: This is too general; 'scope' is the specific PRINCE2 performance aspect that defines the products and work required.
- AXELOS. (2023). Managing Successful Projects with PRINCE2 (7th ed.). TSO (The Stationery Office). Section 4.2.4, p. 34.
- AXELOS. (2023). Managing Successful Projects with PRINCE2 (7th ed.). TSO (The Stationery Office). Section 10.1, p. 108.
Keep practicing
Take the free PRINCE2-FOUNDATION practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PRINCE2-FOUNDATION practice questions
- Question 1How should effective issue management be applied When changing management products?
- Question 3Which is a benefit of using PRINCE2?
- Question 4Which is an assumption about the PRINCE2 customer/supplier environment?
- Question 5What is an advantage of applying the 'manage by stages' principle?
- Question 6Which is a minimum requirement for applying the quality theme?
- Question 7Identify the missing words in the following sentence. The project manager [ ? ] for day-t…