Which two of the following are appropriate topics for discussion during a Sprint Retrospective? (Choose two.)
Full set: 298 questionsThe purpose of the Sprint Retrospective is to plan ways to increase quality and effectiveness. The Scrum Team inspects the last Sprint regarding individuals, interactions, processes, tools, and its Definition of Done. Therefore, discussing how the team collaborates (interactions) and identifying high-priority process improvements are central to this event. The outcome is an actionable plan for improvement in the upcoming Sprint, which may include adding specific improvement items to the next Sprint Backlog.
B. The order of items in the Product Backlog is the accountability of the Product Owner and is typically discussed during Product Backlog refinement, not the Sprint Retrospective.
D. Documenting acceptance criteria is an activity of Product Backlog refinement, which focuses on preparing items for future Sprints, not inspecting the process of the completed Sprint.
1. Schwaber
K.
& Sutherland
J. (2020). The Scrum Guide. Scrum.org.
Page 12
"Sprint Retrospective": "The purpose of the Sprint Retrospective is to plan ways to increase quality and effectiveness. The Scrum Team inspects how the last Sprint went with regards to individuals
interactions
processes
tools
and their Definition of Done." (This supports option C).
Page 12
"Sprint Retrospective": "The Scrum Team identifies the most helpful changes to improve its effectiveness. The most impactful improvements are addressed as soon as possible. They may even be added to the Sprint Backlog for the next Sprint." (This supports option A).
Page 9
"Product Backlog": "The Product Owner is also accountable for effective Product Backlog management
which includes: ... Ordering Product Backlog items". (This supports the reasoning for why option B is incorrect for this event).
2. Dingsøyr
T.
Dybå
T.
& Moe
N. B. (2018). A systematic review of the factors that contribute to the success of software process improvement. IEEE Transactions on Software Engineering
44(6)
588-605. https://doi.org/10.1109/TSE.2017.2699822
Section 3.2.2
"Retrospectives": The paper analyzes retrospectives as a key practice for continuous improvement
emphasizing their role in reflecting on the process and team collaboration to identify actionable improvements
which aligns with options A and C.
3. University of California
Berkeley. (n.d.). CS 169 Software Engineering Course Materials. EECS Department.
In lectures on Agile and Scrum
the Sprint Retrospective is defined as the event for the team to reflect on its own process ("what went well
what could be improved") and create a plan for improvements in the next Sprint. This distinguishes it from product-focused activities like backlog ordering or writing acceptance criteria.
Keep practicing
Take the free PSM-1 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PSM-1 practice questions
- Question 1What is the role of management in Scrum?
- Question 2What are two effective ways for the Scrum Team to make non-functional requirements visibl…
- Question 3When is the Sprint Backlog created?
- Question 4When might a Sprint be abnormally cancelled?
- Question 5What is the tactic a Scrum Master should use to divide a group of 100 people into multipl…
- Question 7When many Scrum Teams are working on the same product, should all of their increments be …