PSP practice question 4 of 35
During project management, which of the following deliverables are part of the design phase?
Full set: 312 questionsDomain Application, Design, and Integration of Physical Security Systems
The design phase of a security project focuses on translating the approved security concepts and recommendations into a detailed, buildable plan. A core deliverable of this phase is the creation of construction documents, which include drawings and specifications. The equipment list, often part of the specifications or a Bill of Materials (BOM), is a fundamental component that details the specific make, model, and quantity of all hardware required for the system. This list is essential for procurement, bidding, and eventual installation, making it a primary output of the design effort.
A. Recommended safeguards and sole-source justification: Recommended safeguards are an output of the preceding risk assessment phase, while sole-source justification is a procurement-related activity.
B. Implementation schedule, bidder instructions, and security-device schedules: These are deliverables for the subsequent procurement and implementation phases, created after the design is complete.
C. Cost evaluations and due-diligence results: Due diligence and preliminary cost estimates are part of the initial survey and assessment phase that informs the design.
1. ASIS International. (2015). Physical Security Principles. Chapter 5
"The Security Project Management Process
" pp. 104-106. This chapter details the project lifecycle
identifying that the design phase results in the creation of construction documents
including detailed specifications of which equipment lists are a key part. The subsequent "Bidding or Procurement Phase" uses these design documents.
2. ASIS International. (2021). Protection of Assets (POA)
Physical Security. "Systems Integration
" Section 5.3.3
"Design Development." This section explains that the design development phase produces a complete set of construction documents
including specifications that "detail the quality and type of materials to be used
" which is effectively the equipment list.
3. Garcia
M. L. (2008). The Design and Evaluation of Physical Protection Systems. Chapter 3
"The Design and Evaluation Process
" p. 33. This source outlines the system design process
noting that a key step is the "Detailed Design
" which involves selecting specific hardware and developing a complete equipment list before proceeding to procurement and installation.
Keep practicing
Take the free PSP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PSP practice questions
- Question 1Some people emerge as experts who then sell their expertise for a fee; these people are c…
- Question 2The concept of __________ arises from agency law in which one party has the power to cont…
- Question 3What allows people to log on to a remote computer and use the resources of that system if…
- Question 5Which of the following is NOT included in the pass systems?
- Question 6Administrative workload is substantially decreased when which service is employed?
- Question 7Private sector will become increasingly involve in crime prevention; public law enforceme…