One of the Scrum events is the Daily Scrum. What are two intended outcomes of the Daily Scrum? (choose the best two answers)
Full set: 178 questionsDomain Scrum Framework
The Daily Scrum is a key inspection and adaptation event for the Developers of the Scrum Team. Its primary purpose is to inspect progress toward the Sprint Goal and to create a plan for the next 24 hours of work. This involves improving communication and promoting quick decision-making. A critical part of this process is identifying any impediments that are blocking progress, which allows the team to address them promptly (D). The outcome of this inspection and planning is a shared understanding among the Developers of the most crucial work to tackle next, ensuring they are aligned and can make the best possible progress toward the Sprint Goal (E).
A. The Daily Scrum is a planning event for the Developers, not a status update for the Scrum Master to plan their work.
B. While the Scrum board is updated, the event's purpose is internal team alignment, not creating a transparency artifact for external stakeholders.
C. The Daily Scrum is a collaborative planning meeting for the team, not an individual status report for upper management.
1. Schwaber
K.
& Sutherland
J. (2020). The Scrum Guide. Scrum.org.
Page 10
"Daily Scrum" section: "The purpose of the Daily Scrum is to inspect progress toward the Sprint Goal and adapt the Sprint Backlog as necessary
adjusting the upcoming planned work." This directly supports option E.
Page 10
"Daily Scrum" section: "The Daily Scrum improves communications
identifies impediments
promotes quick decision-making
and consequently eliminates the need for other meetings." This directly supports option D.
Page 10
"Daily Scrum" section: "The Developers can select whatever structure and techniques they want
as long as their Daily Scrum focuses on progress toward the Sprint Goal and produces an actionable plan for the next day of work." This refutes the idea that it's a status meeting for others (A
C).
Keep practicing
Take the free PSPO-I practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PSPO-I practice questions
- Question 1How often should customer satisfaction be measured? (choose the best answer)
- Question 2True or False: The Scrum Team is accountable for creating a valuable increment every Spri…
- Question 4Which outcome is expected as a Scrum Team matures? (choose the best answer)
- Question 5Who must attend the Daily Scrum? (choose the best answer)
- Question 6During a Sprint, when is new work or further decomposition of work added to the Sprint Ba…
- Question 7As the Developers start work during the Sprint, they realize they have selected too much …