A project manager has stated that he wants 'secure and controlled access to documentation, as well as support for impact analysis and traceability in terms of version history'. What element of requirements management will offer this?
Full set: 40 questionsCorrect Answer:
A. Change control
Explanation
Change control is a systematic approach to managing all changes made to a product or system. The purpose is to ensure that no unnecessary changes are made, that all changes are documented, that services are not unnecessarily disrupted and that resources are used efficiently.
Reference: https://searchdisasterrecovery.techtarget.com/definition/change-control
Keep practicing
Take the free RE18 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other RE18 practice questions
- Question 1ChemCo Ltd has initiated a project to consider changes in its pension scheme. Paul works …
- Question 2In a requirements catalogue, a distinction is often made between business level and solut…
- Question 3At Rusty Springs Ltd, a new online order system is being designed for its registered cust…
- Question 4An international travel operator has a customer services department responsible for inves…
- Question 5An inexperienced business analyst has been asked to conduct scenario analysis. The notes …
- Question 7Peter is analyzing requirements elicited for a sales order system. He is looking at the f…