SAFE-POPM practice question 2 of 10
Which Agile Team event supports relentless improvement?
Full set: 47 questionsThe Iteration Retrospective is a dedicated event held at the end of each Iteration for the Agile Team to reflect on its process and identify improvements. This event is a core component of the team-level Inspect and Adapt cycle and directly embodies the SAFe Core Value of Relentless Improvement. During the retrospective, the team analyzes what went well, what did not, and creates an improvement backlog item to action in the next Iteration. This structured, recurring practice ensures continuous, incremental process enhancement at the team level.
A. Inspect and Adapt is a Program Increment (PI) level event for the entire Agile Release Train (ART), not a specific Agile Team event.
B. The System Demo's primary purpose is to provide feedback on the integrated solution from a stakeholder perspective, not to improve the team's internal processes.
D. The Team Sync is a brief daily meeting focused on coordinating the day's activities and tracking progress towards the Iteration Goal, not on process improvement. ---
1. Scaled Agile, Inc. (2023). Iteration Retrospective. Scaled Agile Framework. Retrieved from https://www.scaledagileframework.com/iteration-retrospective/.
Reference Specifics: The article states, "The Iteration Retrospective is a regular event for the Agile Team to reflect on the Iteration and identify improvements to its process... This is a key part of the team’s Inspect and Adapt (I&A) cycle and directly supports the SAFe Core Value of Relentless Improvement."
2. Scaled Agile, Inc. (2023). Relentless Improvement. Scaled Agile Framework. Retrieved from https://www.scaledagileframework.com/relentless-improvement/.
Reference Specifics: This article defines Relentless Improvement as a core value and highlights the Inspect and Adapt event as the mechanism for the Agile Release Train, distinguishing it from the team-level retrospective.
3. Scaled Agile, Inc. (2023). Inspect & Adapt. Scaled Agile Framework. Retrieved from https://www.scaledagileframework.com/inspect-and-adapt/.
Reference Specifics: The first paragraph clearly defines the I&A as an event for the Agile Release Train: "The Inspect and Adapt (I&A) is a significant event held at the end of each Program Increment (PI), where the current state of the Solution is demonstrated and evaluated by the train."
Keep practicing
Take the free SAFE-POPM practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other SAFE-POPM practice questions
- Question 1In the first step of SAFe's Continuous Delivery Pipeline, Product Owners and Product Mana…
- Question 3What is one input to the Vision?
- Question 4What is defined as a product, service, or system delivered to the Customer?
- Question 5What does a Kanban board demonstrate?
- Question 6Which Product Owner responsibility supports the team with value delivery?
- Question 7What is one method to establish a team's velocity?