SAFE-RTE practice question 23 of 30

Product Management wants to prioritize a list of Features likely to be planned in the up-coming Program Increment (PI) meeting. What should Product Management use as the denominator of the weighted shortest job first calculation?

Full set: 219 questions
Answer options
A: The T-shirt sizes for each of the Features
B: The actual business value of each Feature
C: Feature size expressed in story points
D: Job size based on relative estimation Correct answer
Correct Answer:
D. Job size based on relative estimation
Explanation

When Product Management wants to prioritize a list of Features likely to be planned in the upcoming Program Increment (PI) meeting, they should use the job size based on relative estimation as the denominator of the Weighted Shortest Job First (WSJF) calculation. This approach helps in effectively ranking the features based on their size and estimated effort.