SAFE-RTE practice question 15 of 30
While facilitating Program Increment (PI) Planning readiness activities, the Release Train Engineer (RTE) notices a Feature that is risky to the teams because the technology is new. Which of the following could reduce the risk?
Full set: 219 questionsIn SAFe, when a Release Train Engineer (RTE) identifies a feature that is risky due to new technology, one of the strategies to reduce the risk is to coach the teams to create exploration Enablers. Exploration Enablers are a type of backlog item that supports research, prototyping, and other activities needed to develop an understanding of customer needs and the technology itself2. This approach allows teams to explore and gain familiarity with the new technology in a controlled environment, reducing uncertainty and risk before committing to the full implementation during Program Increment (PI) Planning2. It is part of the Continuous Exploration process, which is key to fostering innovation and aligning the solution with customer needs1.
Keep practicing
Take the free SAFE-RTE practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other SAFE-RTE practice questions
- Question 1What is a characteristic of an effective Scrum Master?
- Question 2Which one SAFe core value creates an environment where facts are always friendly?
- Question 3Which of the Core Competencies of Business Agility includes aligning strategy with execut…
- Question 4In the SAFe work item hierarchy, Features are decomposed into what?
- Question 5Why do teams have an Iteration retrospective?
- Question 6Which of the following is true about the ART sync event?