SAFE-RTE practice question 15 of 30

While facilitating Program Increment (PI) Planning readiness activities, the Release Train Engineer (RTE) notices a Feature that is risky to the teams because the technology is new. Which of the following could reduce the risk?

Full set: 219 questions
Answer options
A: Ensure engineering managers are directing the development process
B: Coach the teams to create exploration Enablers Correct answer
C: Ask for a presentation of a detailed design before the PI Planning meeting
D: Make sure all the technical specifications are written before PI execution
Correct Answer:
B. Coach the teams to create exploration Enablers
Explanation

In SAFe, when a Release Train Engineer (RTE) identifies a feature that is risky due to new technology, one of the strategies to reduce the risk is to coach the teams to create exploration Enablers. Exploration Enablers are a type of backlog item that supports research, prototyping, and other activities needed to develop an understanding of customer needs and the technology itself2. This approach allows teams to explore and gain familiarity with the new technology in a controlled environment, reducing uncertainty and risk before committing to the full implementation during Program Increment (PI) Planning2. It is part of the Continuous Exploration process, which is key to fostering innovation and aligning the solution with customer needs1.