SAFE-SASM practice question 15 of 15

Which two statements are true about a Feature? (Choose two.)

Full set: 60 questions
Answer options
A: It is developed within a single Agile Team
B: It is fully completed by a single Agile Release Train within one PI Correct answer
C: It is prioritized using weighted shortest job first Correct answer
D: It has one Capability as a parent
Correct Answer:
B. It is fully completed by a single Agile Release Train within one PI; C. It is prioritized using weighted shortest job first
Explanation

Completed by a Single Agile Release Train within one PI: Definition: A Feature in SAFe is a service or functionality that meets the needs of a customer and can be delivered within a single Program Increment (PI) by an ART.
Explanation: Features are planned and delivered within the timeframe of a PI, ensuring that they provide tangible value and align with the ART's objectives. Prioritized using Weighted Shortest Job First (WSJF): Definition: WSJF is a prioritization method used in SAFe to sequence work for maximum economic benefit.
Explanation: Features are prioritized based on their cost of delay and the effort required to implement them. This ensures that the most valuable and impactful features are delivered first. SAFe Scrum Master Reference: SAFe framework details the concept of Features, emphasizing their completion within a PI and their prioritization using WSJF to maximize value delivery.

Scroll to Top