How does a team calculate its initial velocity during its first PI Planning meeting when teams don't have historic data?
Full set: 179 questionsCorrect Answer:
D. Assign 10 points per team member (not counting the Scrum Master and Product Owner) and
subtract 1 point for each holiday or vacation day.
Explanation
SAFe’s guidance for new teams without historical velocity is to assign 8–12 points per team member (typically 10) except Scrum Master and Product Owner, subtracting points for planned absences. “For initial velocity, a simple guideline is to assume 8–12 points per team member (excluding Scrum Master and Product Owner), then subtract 1 point for each day of vacation or holiday.” (Source: SAFe 6.0 Framework: PI Planning Preparation)
Keep practicing
Take the free SAFE-SPC practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other SAFE-SPC practice questions
- Question 1What is one way Design Thinking measures success?
- Question 2When is the best time to release a product or Solution to the marketplace?
- Question 3Which activity is associated with the release-on-demand step of the continuous delivery p…
- Question 4What description best represents Capabilities as defined in SAFe?
- Question 5What activity calls for using the ROAM technique?
- Question 6You are working with an ART that is preparing for their first PI Planning event. All Feat…