SAFE-SPC practice question 23 of 25

SAFe assumes that programs commit to the key priorities within the current PI and provide a forecast for a few subsequent PIs.

Full set: 179 questions
Answer options
A: True Correct answer
B: False
Correct Answer:
A. True
Explanation

During PI Planning, ARTs (programs) commit to the PI Objectives for the current Program Increment (PI) and, when possible, provide a forecast for the next few PIs. This is a key part of SAFe’s planning and transparency practices. “During PI Planning, teams commit to the objectives for the current PI and may provide a forecast for future PIs to aid in longer-term planning and alignment.” (Source: SAFe 6.0 Framework: PI Planning; SPC 6.0 Guide, “Coaching ART Execution”) ===========