SALES-CLOUD-CONSULTANT practice question 12 of 25

Cloud Kicks (CK) has requested a Statement of Work (SOW) that clearly details who will train users on new features and how the training will be delivered. Which section of a SOW should the consultant discuss with CK to meet the requirement?

Full set: 190 questions
Answer options
A: Scope Correct answer
B: Background
C: Terms and Conditions
Correct Answer:
A. Scope
Explanation

The Scope section of a Statement of Work (SOW) is the most critical component for defining the project's boundaries, deliverables, and specific tasks. It explicitly details the work to be performed by the consultant. This includes activities such as user training, specifying who is responsible for delivering the training (the consultant, the client, or a third party) and the methodology (e.g., virtual, in-person, train-the-trainer). Placing these details in the scope ensures there is a clear, mutual understanding of the project's deliverables and prevents "scope creep."

Why Incorrect

B. Background: This section provides context for the project, such as the business challenges and objectives, but does not detail the specific tasks or deliverables.
C. Terms and Conditions: This section outlines the legal and financial aspects of the engagement, including payment schedules, confidentiality, and liability, not the operational plan for project activities.

References

1. Project Management Institute (PMI), A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Sixth Edition. In Section 12.1.1.6, "Procurement Statement of Work," the guide explains that the SOW describes the project's deliverables in sufficient detail. It states the SOW should be "clear, complete, and concise" and can include "the work to be performed" and "the approach the seller will take to accomplish the work." This directly aligns with defining who will train and how.

2. Boutselis, M. A. (2009). A Standardized Approach for Writing a Statement of Work (Master's thesis, Massachusetts Institute of Technology). In Chapter 2, "The SOW Document," the author states, "The Scope of Work section is arguably the most important section of the SOW... It should describe the work to be done in detail and specify the deliverables." This academic source confirms that detailed tasks, such as a training plan, are a core component of the Scope section. (Available via MIT DSpace).

Scroll to Top