National Institute of Standards and Technology (NIST)
Source: NIST Special Publication 800-34 Rev. 1, "Contingency Planning Guide for
Federal Information Systems."
Details:
Hot Site: "A fully equipped alternate processing site that is ready to be occupied and
begin operations within a short period of time (e.g., hours or days)." (Section 3.3.3,
Page 17)
Warm Site: "A partially equipped alternate processing site that contains some or all of
the system hardware, software, telecommunications, and power sources." (Section
3.3.3, Page 18)
Cold Site: "A facility that provides the basic environment (e.g., electrical wiring, air
conditioning, plumbing) for IT systems, but does not include any pre-installed IT
hardware or software." (Section 3.3.3, Page 18)
URL: https://csrc.nist.gov/publications/detail/sp/800-34/rev-1/final (PDF page 27 for
section 3.3.3)
Microsoft Azure Documentation (Vendor Documentation - representative of industry
understanding of these terms)
Source: Microsoft Azure, "Replicate Azure VMs to another Azure region" (While specific
to Azure, it describes common DR concepts). Disaster recovery and business continuity
planning often use these standard site type definitions.
Details: Hot sites are characterized by their ability to support rapid failover. The
documentation on Azure Site Recovery inherently supports the concept of quick
recovery to a secondary location, which aligns with a hot site's purpose if configured for
minimal RTO. For instance, "Azure Site Recovery contributes to your business
continuity and disaster recovery (BCDR) strategy by keeping your business apps up
and running during planned and unplanned outages." The speed of recovery ("within
minutes") often facilitated by such services mirrors the operational readiness of a hot
site.
URL:
https://learn.microsoft.com/en-us/azure/site-recovery/azure-to-azure-tutorialenable-replication (General concept, not a direct definition page for hot/cold/warm, but
illustrates the goal of quick recovery which hot sites provide).
IEEE Xplore (Peer-reviewed academic publication)
Source: Ionita, M., & Ionita, A. (2017). "Disaster Recovery and Business Continuity using
Virtualization Technologies." 2017 16th RoEduNet Conference: Networking in Education
and Research (RoEduNet).
Details: "A hot site is a fully operational data center with hardware and software, data is
mirrored from the primary site, and staff ready to resume operations in case of disaster.
Recovery time is minimal (hours)." (Section III.A) "A warm site is a compromise
between a hot site and a cold site. It has the hardware installed but the latest data
backup needs to be restored. Recovery time is between several hours and a few days."
(Section III.A) "A cold site is an empty data center with power and cooling. Equipment
and data must be brought in and configured. Recovery time may take weeks or even
more." (Section III.A)
DOI: https://doi.org/10.1109/ROEDUNET.2017.8125139 (Page 2 of the PDF, section III.A)