What is an objective of the Discovery and Strategy stage of the SIAM roadmap?

Full set: 40 questions
Answer options
A: complete the design of the SIAM model
B: establish the SIAM transition project Correct answer
C: put in place and in use the new SIAM model
D: obtain full approval of the SIAM model
Correct Answer:
B. establish the SIAM transition project
Explanation

The Discovery and Strategy stage is the first phase of the SIAM roadmap. Its primary objective is to investigate the current environment, define the organization's goals for moving to a SIAM model, and develop a high-level strategy and business case. The culmination of this stage is a "go/no-go" decision. Upon receiving approval for the business case, the formal SIAM transition project is established to carry out the subsequent stages of the roadmap. This makes establishing the project a key objective and outcome of this initial phase.

Why Incorrect

A. complete the design of the SIAM model: The detailed design of the SIAM model is completed during the second stage, 'Plan and Build', not the initial 'Discovery and Strategy' stage.
C. put in place and in use the new SIAM model: This activity occurs during the 'Implement' stage, which follows the 'Plan and Build' stage. It is the phase where the designed model becomes operational.
D. obtain full approval of the SIAM model: Approval is sought for the business case and high-level strategy, not the "full" detailed model, which has not yet been designed at this early stage.

References

1. Scopism. (2020). Service Integration and Management (SIAM™) Foundation Body of Knowledge.

Section 4.1.1, Discovery & Strategy: This section outlines the activities of the first stage, stating, "The key outputs are the approved business case and the high-level SIAM design and operating model... The organization makes a ‘go/no-go’ decision about whether to proceed with the SIAM transition." A 'go' decision directly leads to the establishment of the transition project (Option B).

Section 4.1.2, Plan & Build: This section confirms that detailed design occurs here, making option A incorrect. "During this stage, the detailed SIAM model is designed..."

Section 4.1.3, Implement: This section describes the implementation activities, making option C incorrect. "This stage focuses on the implementation of the SIAM model..."