Workday-Pro-Time-Tracking practice question 1 of 10
You have configured a time calculation to identify when a worker has reached or exceeded a number of consecutive days worked. You must now configure a time calculation for hours worked over 8 hours on the seventh consecutive day. How do you assign priority to ensure the time is processed correctly?
Full set: 55 questionsThe two calculations are dependent: the overtime calculation for the seventh day can only run after another calculation has successfully identified and tagged that day as the seventh consecutive day. In Workday, dependent calculations require manual prioritization. The calculation that identifies the condition (the 7th day) must be assigned a higher priority (a lower number, e.g., 100) so it executes first. The calculation that acts on that condition (overtime on the 7th day) must be assigned a lower priority (a higher number, e.g., 200) to ensure it runs afterward.
A. Workday does not automatically determine the logical priority for complex, dependent calculations; this must be configured by an administrator.
B. Time Tracking Eligibility Rules determine which workers are subject to a calculation, not the execution order of multiple calculations for an eligible worker.
D. Assigning calculations to a group is a prerequisite for prioritization, but it does not by itself set the correct execution order within that group.
1. Workday Time Tracking Administrator Guide. Section: "Time Calculation Priorities". The guide specifies that calculations with dependencies, where one calculation's output is the input for another, must be ordered using the Maintain Time Calculation Priorities task.
2. Workday Community, Article ID: 21455. "Configuring Dependent Calculations". This article provides examples of setting up multi-step calculations, emphasizing that the prerequisite calculation must always be given a higher priority (lower priority number) to ensure it runs first.
Keep practicing
Take the free Workday-Pro-Time-Tracking practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other Workday-Pro-Time-Tracking practice questions
- Question 2The time tracking administrator asks you to confirm that workers are reporting their sche…
- Question 3A worker’s Work Schedule Calendar has a Day Breaker of 2:00 AM (current day from previous…
- Question 4How are Time Tracking Calculations assigned to workers?
- Question 5You are creating a time block conditional calculation. What business object can you use t…
- Question 6You have configured a Time Calculation that tags all hours reported on either Saturday or…
- Question 7You need to create a validation that warns a worker if they have multiple time blocks wit…