1Z0-1057-26 practice question 15 of 25
You are managing a project based on a Waterfall model. You define a project and a project plan in Oracle Project Portfolio Management with tasks and…
Full set: 126 questionsA deliverable that you link to a requirement remains associated only with that requirement; it is NOT propagated automatically to the tasks later created for the requirement. Conversely, you can associate a deliverable directly with any project task even when the requirement itself is not linked to that task. Therefore option C and option D correctly describe the inheritance behaviour.
A. States that deliverable–task association happens automatically, which the application does not perform.
B. Implies deliverable–task linkage is dependent on requirement–task linkage; in fact the association is independent.
1. Oracle Fusion Cloud Project Execution Management 23B, Using Requirements and Deliverables, chapter “Manage Deliverables”, section “Deliverable Associations”, pp. 46-47.
2. Oracle Fusion Cloud Project Execution Management 23B Implementation Guide, section “Requirements-to-Task and Deliverable Relationships”, para. 2.
Keep practicing
Take the free 1Z0-1057-26 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other 1Z0-1057-26 practice questions
- Question 1While creating a new project template, you notice that a default Asset Cost Allocation me…
- Question 2Your customer wants to calculate Estimate to Complete (ETC) as the difference between Cur…
- Question 3Which step within the functional setup manager helps you to move your verified setup data…
- Question 4Which three Cost Collection Flexfield core attributes can be derived during import if not…
- Question 5You have been asked to set up one active person, who is not a team member in the project,…
- Question 6Your customer wants a team member who is assigned to a project to be able to create and s…