You are managing a project based on a Waterfall model. You define a project and a project plan in Oracle Project Management with tasks and subtasks…
Full set: 126 questionsIn Oracle Project Management, requirements, tasks, and deliverables are distinct objects whose relationships are managed explicitly. You can associate a deliverable directly with a project task, regardless of whether a requirement is also associated with that task. The associations are independent. Furthermore, if you associate a deliverable with a requirement, that association is not automatically inherited by any tasks that are subsequently created for or associated with that same requirement. The project manager must create the association between the deliverable and the task separately.
A. Associating a deliverable with a task is not dependent on a requirement; deliverables can be linked to any task, such as project management overhead tasks.
C. The system does not automatically associate a requirement's deliverable with a task. This association must be created manually by the user.
1. Oracle Fusion Applications Help
"Using Project Execution Management"
Chapter: Manage Project Deliverables
Section: "Project Deliverables: Explained". This document explains that deliverables can be associated with tasks to track progress.
2. Oracle Fusion Applications Help
"Using Project Execution Management"
Chapter: Define and Manage Project Requirements
Section: "How Project Requirements Work with Other Objects". This section details how requirements associate with tasks
but makes no mention of automatic deliverable inheritance.
Keep practicing
Take the free 1Z0-1057-26 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other 1Z0-1057-26 practice questions
- Question 1While creating a new project template, you notice that a default Asset Cost Allocation me…
- Question 2Your customer wants to calculate Estimate to Complete (ETC) as the difference between Cur…
- Question 3Which step within the functional setup manager helps you to move your verified setup data…
- Question 4Which three Cost Collection Flexfield core attributes can be derived during import if not…
- Question 5You have been asked to set up one active person, who is not a team member in the project,…
- Question 6Your customer wants a team member who is assigned to a project to be able to create and s…