1Z0-1057-26 practice question 10 of 25
You have a billable project for which the following details are provided: Associated Inception-To-Date (ITD) Project Actual Cost: USD 60 Associated…
Full set: 126 questionsYou have a billable project for which the following details are provided: Associated Inception-To-Date (ITD) Project Actual Cost: USD 60 Associated Project Budgeted Cost: USD 300 Contract Amount: USD 1000 Project Funded Amount: USD 750 Sum of Existing Revenue Events: USD 80 Identify the Associated Project Spent revenue that will get generated based on the preceding details. (Choose the best Answer)
This scenario uses the Percent Spent revenue recognition method. The Inception-To-Date (ITD) revenue is calculated as (ITD Actual Cost / Budgeted Cost) Contract Amount. Calculation: (USD 60 / USD 300) USD 1000 = 0.20 1000 = USD 200. This calculated ITD revenue (USD 200) is less than the funded amount (USD 750), so it is not limited. The revenue to be generated in the current period is the calculated ITD revenue minus any existing revenue: USD 200 - USD 80 = USD 120.
A. USD 184 is an incorrect calculation. It does not follow the standard Percent Spent revenue formula.
C. USD 134 is an incorrect calculation. It does not align with the formula for Percent Spent revenue recognition.
D. USD 70 is an incorrect calculation. It might result from misinterpreting the inputs for the revenue formula.
1. Oracle Fusion Cloud Project Management, Using Project Billing, Release 24B, Chapter 4: Recognize Revenue, Section: "How Project and Contract Revenue is Calculated". The guide explains that for percent spent methods, revenue is calculated as (actual cost / budget cost) contract amount, and the current period's revenue is the difference between the new ITD amount and previously recognized amounts.
2. Oracle Fusion Cloud Project Management, Implementing Project Financial Management, Release 24B, Chapter 11: Set Up Project Revenue, Section: "Revenue Method: Percent Spent". This section details the formula: "Percent spent revenue amount = (actual cost to date / budget or forecast cost) (budget or forecast revenue)."
Keep practicing
Take the free 1Z0-1057-26 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other 1Z0-1057-26 practice questions
- Question 1While creating a new project template, you notice that a default Asset Cost Allocation me…
- Question 2Your customer wants to calculate Estimate to Complete (ETC) as the difference between Cur…
- Question 3Which step within the functional setup manager helps you to move your verified setup data…
- Question 4Which three Cost Collection Flexfield core attributes can be derived during import if not…
- Question 5You have been asked to set up one active person, who is not a team member in the project,…
- Question 6Your customer wants a team member who is assigned to a project to be able to create and s…