ACP-620 practice question 2 of 15
A team needs a board that meets these requirements: ● All issues can be moved across the entire workflow on a single view of the board. ● Issues can be worked in a continuous flow without start and stop dates. Which board configuration meets the requirements?
Full set: 56 questionsCorrect Answer:
A. Kanban board without backlog
Explanation
A Kanban board without backlog displays all issues on a single view and supports a continuous workflow without start and stop dates. This setup is ideal for teams using a continuous delivery process, allowing issues to move freely across the entire workflow.
Keep practicing
Take the free ACP-620 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other ACP-620 practice questions
- Question 15 development teams need to work across 3 projects and plan their iterations in a single …
- Question 3Your team wants to measure their performance based on the number of issues completed in e…
- Question 4Your team wants to see the average number of days that resolved issues were open over a g…
- Question 5The UX team uses a custom issue type named Design in your team-managed project. You want …
- Question 6Project administrators need the ability to send customized emails to various groups durin…
- Question 7You work in a company-managed project, and your team needs a new field called Colors. Tea…