ACP-620 practice question 3 of 15

Your team wants to measure their performance based on the number of issues completed in each sprint. Currently, they are measured based on the number of story points completed instead. Which board configuration needs to be changed?

Full set: 56 questions
Answer options
A: Column Constraint
B: Maximum constraints
C: Estimation Statistic Correct answer
D: Time Tracking
Correct Answer:
C. Estimation Statistic
Explanation

The Estimation Statistic setting on the Scrum board controls whether performance is measured by story points, issue count, or other metrics. To measure performance based on the number of issues completed instead of story points, you need to change this setting to Issue Count.