How does agile address the risk associated with the project not being fully understood at the beginning?
Full set: 132 questionsAgile addresses the risk of incomplete initial understanding by avoiding too much detail at the start. This approach acknowledges that requirements will evolve and change as the project progresses. Instead of attempting to define everything upfront when knowledge is limited, Agile uses iterative development cycles to progressively elaborate details based on learning and feedback. This reduces the risk of investing heavily in detailed plans that may become obsolete as understanding improves.
A. Allowing a lot of detail contradicts Agile's principle of embracing change and uncertainty.
C. Requiring details at the start goes against Agile's iterative and adaptive approach.
D. Preventing analysis is incorrect; Agile encourages analysis but in iterations, not prevention.
- PRINCE2 Agile® (2015), AXELOS, Chapter 6 "What to fix and what to flex", pp. 67-69
- PRINCE2 Agile® (2015), AXELOS, Chapter 7 "Agile concepts and techniques", Section 7.1, pp. 73-75
- PRINCE2 Agile® (2015), AXELOS, Chapter 20 "The Agilometer", pp. 217-220
- Managing Successful Projects with PRINCE2® (2017), AXELOS, Chapter 3 "Principles", pp. 31-33
Keep practicing
Take the free AGILE-FOUNDATION practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other AGILE-FOUNDATION practice questions
- Question 1When tracking progress, which term describes using agile techniques at the delivery level…
- Question 2Which statement describes the Kanban approach?
- Question 3Which of the following is an example of 'being agile' rather than just ‘doing agile’?
- Question 4What is the purpose of the 'progress' practice?
- Question 5To help with prioritization, what is MOST important when understanding the difference bet…
- Question 6What is the MOST important when blending PRINCE2 Project Management with agile?