AGILE-FOUNDATION practice question 1 of 25

When tracking progress, which term describes using agile techniques at the delivery level, and traditional techniques at the direction and management levels?

Full set: 132 questions
Answer options
A: Preferable
B: Typical Correct answer
C: Effective
Correct Answer:
B. Typical
Explanation

The PRINCE2 Agile guidance describes the common integration of methods as a 'typical' scenario. In this blend, PRINCE2 is used for project direction and management, providing governance and control. Agile methods, such as Scrum or Kanban, are then used at the delivery level for product creation. This structure leverages the strengths of both approaches: PRINCE2 for robust governance and agile for iterative and flexible product delivery. This is not necessarily the only 'effective' or 'preferable' way, but it is the most common and typical application described.

Why Incorrect

A. 'Preferable' is a subjective term; other blends might be preferable depending on the specific project context and environment.
C. While this blend is intended to be effective, 'typical' is the specific term used in the official guidance to describe this common configuration.
Note: The provided answer 'C' is incorrect. The term used in the official manual to describe this scenario is 'typical'.

References

- AXELOS. (2018). PRINCE2 Agile® Foundation. TSO (The Stationery Office). Section 4.3.1, p. 29. "How do PRINCE2 and agile fit together? ... A typical situation would be to use PRINCE2 for project direction and project management, and to use agile for product delivery."