Which role is responsible for facilitating the Agilometer assessment?

Full set: 132 questions
Answer options
A: Project board
B: Project manager Correct answer
C: Team manager
D: Customer subject matter expert
Correct Answer:
B. Project manager
Explanation

The Agilometer is a tool used to assess the risks and opportunities of applying agile in a specific project environment. The project manager is responsible for tailoring the PRINCE2 method to suit the project context. Therefore, the project manager facilitates the Agilometer assessment, typically in a workshop with key stakeholders, to inform how the method should be tailored and to highlight areas that may need particular attention throughout the project.

Why Incorrect

A. The project board reviews the output and implications of the Agilometer assessment but does not facilitate the process itself.
C. The team manager is a key participant in the assessment, providing a delivery-level perspective, but does not hold facilitation responsibility.
D. A customer subject matter expert provides crucial input on requirements and the business environment but is a participant, not the facilitator.

References

- AXELOS. (2015). PRINCE2 Agile®. TSO (The Stationery Office). Section 7.4, p. 60. "The assessment is best carried out as a workshop and should be facilitated by the project manager."