API-580 practice question 5 of 25
Process used to compare the estimated risk against given risk criteria to determine the significance of the risk.
Full set: 140 questionsRisk evaluation is a core component of the risk analysis process. After risk has been identified and estimated (quantified), it must be compared against predefined risk criteria or targets. This comparison determines the significance of the risk and informs decisions on whether the risk is acceptable or requires treatment. The process is fundamental to prioritizing mitigation actions and allocating resources effectively within a risk management framework.
B. Risk estimation is the process of assigning values to the probability and consequence of a risk, which occurs before the evaluation step.
C. Risk identification is the initial step of finding, listing, and characterizing potential risks, not comparing them against criteria.
1. API 580, "Risk-Based Inspection," Third Edition, February 2016, Section 3.1.69, "Risk Evaluation."
2. API 580, "Risk-Based Inspection," Third Edition, February 2016, Section 6.3, "Risk Analysis and Management," Figure 2.
Keep practicing
Take the free API-580 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other API-580 practice questions
- Question 1Reliability efforts, such as reliability centered maintenance (rem), can be linked with r…
- Question 2Qualitative consequence analysis of failure can be estimated separately for each unit, sy…
- Question 3Rbi may include methodologies to assess the effectiveness of the management systems in ma…
- Question 4Potential source of errors in rbi analysis regarding data quality are the following except
- Question 6When some risk identified as acceptable then one of the following is not required.
- Question 7Following are the critical variables for deterioration mechanism except