API-580 practice question 6 of 25
When some risk identified as acceptable then one of the following is not required.
Full set: 140 questionsWhen risk is identified as acceptable, actions to lower that risk are not required. Risk mitigation is defined as the process of modifying a risk to reduce it to an acceptable level. If the risk is already acceptable, this process is not necessary. Similarly, risk reduction, the general process of lowering risk, is also not required. Risk evaluation, however, is the process that must be completed to determine that the risk is acceptable in the first place. Therefore, both risk reduction and risk mitigation are not required.
B. Risk evaluation: This process is required to determine if the risk is acceptable or not. It precedes the decision.
D. Risk control: This is a broad term for managing risk, often involving risk reduction measures, which are not required for acceptable risks.
1. API Recommended Practice 580, Risk-Based Inspection, Third Edition, 2016. Section 3.1.71, "Risk Mitigation: The process of modifying a risk to reduce it to an acceptable level."
2. API Recommended Practice 580, Risk-Based Inspection, Third Edition, 2016. Section 3.1.68, "Risk Evaluation: Process used to compare the estimated risk against given risk criteria to determine the significance of the risk."
3. API Recommended Practice 580, Risk-Based Inspection, Third Edition, 2016. Section 3.1.70, "Risk Reduction: The process of lowering the level of risk."
Keep practicing
Take the free API-580 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other API-580 practice questions
- Question 1Reliability efforts, such as reliability centered maintenance (rem), can be linked with r…
- Question 2Qualitative consequence analysis of failure can be estimated separately for each unit, sy…
- Question 3Rbi may include methodologies to assess the effectiveness of the management systems in ma…
- Question 4Potential source of errors in rbi analysis regarding data quality are the following except
- Question 5Process used to compare the estimated risk against given risk criteria to determine the s…
- Question 7Following are the critical variables for deterioration mechanism except