API-936 practice question 10 of 10
[Inspection and Testing Requirements] Which of the following is the appropriate term for testing refractory that was sampled during project site installation in order to confirm that it meets specified physical property standards?
Full set: 85 questionsDomain Test Procedures
As-installed testing is the correct term for the evaluation of refractory samples taken from the actual installation. This testing is performed to verify that the physical properties of the refractory material, after being mixed and applied on-site, meet the project's specified requirements. It confirms the quality of both the material and the installation workmanship, accounting for variables like water content, mixing procedure, and application technique. This is distinct from pre-qualification testing, which is done on the material before it is shipped to the site.
A. Hammer testing: This is a qualitative, non-destructive inspection method used after curing to check for voids or delamination, not a quantitative test of physical properties on a sample.
B. Pre-qualification testing: This testing is performed on refractory materials before installation to qualify the manufacturer's product, not on samples taken from the actual on-site installation.
D. Visual testing: This is a form of inspection to identify surface defects, improper application, or other visible flaws. It does not involve taking samples to measure physical properties.
1. American Petroleum Institute (API) Standard 936
4th Edition
December 2014. Refractory Installation Quality Control—Inspection and Testing Monolithic Refractory Linings and Materials.
Section 3.1.4: Defines "as-installed testing" as "Testing to determine physical properties of refractory materials taken from the installation." This directly supports the correct answer.
Section 3.1.31: Defines "pre-installation testing (qualification testing)" as "Testing to determine physical properties of refractory materials before installation..." This clarifies why option B is incorrect.
Annex A
Section A.4.3.1: Lists "Hammer testing" as a post-installation inspection activity to check for voids
confirming it is an inspection technique
not the term for sample testing.
Keep practicing
Take the free API-936 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other API-936 practice questions
- Question 1[Installation Procedures] The mock-up for vibration cast installations demonstrates the a…
- Question 2[Installation Procedures] A pigment shall be used in the curing compound in order to:
- Question 3[Material Requirements] Which of the following is false per the requirements of API Stand…
- Question 4[Documentation and Records] Who is responsible for ensuring that the material and applica…
- Question 6[Material Requirements] The physical attributes testing of manufactured bricks during pre…
- Question 7[Responsibilities and Qualifications] The installation contractor is required to secure a…