After stakeholders formally signed off on requirements, the business analyst (BA) received numerous emails requesting changes to Salesforce during uses acceptance testing (UAT). The BA quickly became overwhelmed by the requests and needs a way to organize and peritonitis them. What should the BA use to help them organize these requests?

Full set: 310 questions
Answer options
A: Change request log Correct answer
B: Scope statement specification
C: Gap analysis document
Correct Answer:
A. Change request log
Explanation

A change request log is the appropriate tool for systematically managing changes requested after requirements have been formally approved. It allows the business analyst to capture, document, track, and prioritize each request. This organized approach ensures that all proposed changes are evaluated for their impact on scope, budget, and timeline before being approved, rejected, or deferred. It prevents the BA from being overwhelmed and provides transparency to stakeholders.

Why Incorrect

B. A scope statement specification defines the project boundaries at the beginning; it is not a tool for managing incoming change requests during testing.
C. A gap analysis document is created during the analysis phase to identify differences between current and future states, not to manage changes during UAT.

References

1. Salesforce Trailhead, Salesforce Agile Basics, Unit: "Manage Product Changes". This module explains the importance of a structured process for handling changes, such as a backlog or log, to assess impact and prioritize work, which is the function of a change request log.

2. Salesforce Trailhead, Business Analyst Best Practices: Requirements, Unit: "Manage Requirements". This unit describes the need for a formal process to manage requirement changes throughout the project lifecycle to control scope creep, for which a change log is a standard tool.

Scroll to Top