BUSINESS-ANALYST practice question 34 of 35

Northern Trail Outfitters is undergoing a service Cloud implementation and has decided to use the Scrum methodology for the implementation. A business analyst (BA) received an urgent, high- priority change request in the middle of a sprint. Which step should the BA take next?

Full set: 310 questions
Answer options
A: Begin working on the change request as soon as the team has capacity.
B: Add the change request to the prioritized for the next sprint. Correct answer
C: De-prioritize some user stories and add the change request to the current sprint.
Correct Answer:
B. Add the change request to the prioritized for the next sprint.
Explanation

According to the Scrum framework, the sprint backlog is considered locked once a sprint begins to allow the development team to focus on their commitment. An urgent, high-priority change request should be added to the product backlog by the Business Analyst (BA) or Product Owner. It will then be prioritized against other items in the backlog and can be considered for inclusion in the next sprint during the sprint planning meeting. This maintains the integrity and focus of the current sprint.

Why Incorrect

A. Begin working on the change request as soon as the team has capacity: This disrupts the planned sprint and undermines the team's commitment and ability to forecast work.
C. De-prioritize some user stories and add the change request to the current sprint: This is an exceptional action, often requiring the sprint to be cancelled and restarted. It is not the standard next step for handling a new request.

References

1. Salesforce Trailhead, "Agile Basics" module, "Scrum and Kanban at Salesforce" unit. This unit explains the Scrum process, stating, "Once the sprint begins, the team can’t add new stories to the sprint." It reinforces that new work is added to the backlog for future sprints.

2. The Scrum Guide (Scrum.org), November 2020 edition, "The Sprint" section (p. 9). The guide states, "No changes are made that would endanger the Sprint Goal...Scope may be clarified and re-negotiated with the Product Owner as more is learned." This emphasizes protecting the sprint goal from disruptive new requests.

3. Salesforce Trailhead, "Scrum and the Business Analyst" module, "Manage the Product Backlog" unit. This unit describes the BA's role in managing the backlog, which is the appropriate repository for new and incoming requests that arise during a sprint.