CBCI practice question 2 of 10
Strategic, tactical, and operational plans should always be activated:
Full set: 176 questionsThe activation of strategic, tactical, and operational plans must be proportionate to the nature and scale of the incident. Each level of the response structure should have its own plan with clearly defined activation triggers, roles, and responsibilities. An incident may only require an operational response, while a more severe event could escalate, triggering tactical and then strategic plans. This approach ensures a scalable and appropriate response, avoiding unnecessary resource allocation or escalation. Activation is therefore determined by the specific conditions documented within the relevant plan for that team or level.
A. Simultaneous activation is inefficient and often inappropriate, as many incidents only require an operational-level response.
B. This implies an "all-or-nothing" approach, which is inflexible and prevents a scalable response to smaller incidents.
C. Activation is not exclusively a top-down process; an incident can be identified and managed at the operational level without strategic involvement.
1. Business Continuity Institute (BCI)
Good Practice Guidelines (GPG)
2018 Edition.
Section 8.3.3
Plan Activation: "The plan should clearly state the circumstances under which it should be activated... The activation criteria should be clear
concise and easy to understand
avoiding any ambiguity." This directly supports that activation is based on documented conditions within the relevant plan.
Section 8.2
Response Structure: The GPG describes the three-tiered (Strategic
Tactical
Operational) structure
noting that it provides a "scalable response to any incident." This scalability refutes the simultaneous
all-or-nothing
or purely top-down activation models proposed in the incorrect options.
2. ISO 22301:2019
Security and resilience — Business continuity management systems — Requirements.
Clause 8.4.2
Warning and communication: This clause requires procedures for internal and external communication upon incident detection.
Clause 8.4.4
Business continuity plans and procedures: Requires that procedures "contain the criteria and process for their activation." This aligns with the principle that each plan has its own documented activation triggers.
Keep practicing
Take the free CBCI practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other CBCI practice questions
- Question 1When selecting solutions to mitigate unacceptable risks and single points of failure, the…
- Question 3Which of the following is a principle to be adhered to when producing communications duri…
- Question 4One of the steps in the risk management process is to establish the risk treatment requir…
- Question 5The scope of the Business Continuity Management System (BCMS) should be reviewed if:
- Question 6Which of the following statements best describes the relationship between Business Contin…
- Question 7As part of the preparation for responding to an incident, plans should be in place to ena…