CCBA practice question 23 of 35
A business analyst (BA) is working on a project that has a release date that cannot be changed. The BA engaged with stakeholders and completed the…
Choose your answer, then check it against the explanation.
A business analyst (BA) is working on a project that has a release date that cannot be changed. The
BA engaged with stakeholders and completed the business requirements elicitation task. Upon
review with the rest of the project team, it is determined that not all requirements can be
implemented by the set deadline. What must the BA do to ensure maximum business value?
Question 23 of 35
Keep practicing
Take the free CCBA practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other CCBA practice questions
- Question 1Kendra is the business analyst for her organization. She's working with the project manag…
- Question 2You are the business analyst for your organization and you're working with Adam on busine…
- Question 3What condition of the requirements must be fulfilled in order to use the matrix documenta…
- Question 4Shelly is the business analyst for her organization and she's working with Thomas to revi…
- Question 5Linda is the business analyst for her organization and she's working with Joe, a new busi…
- Question 6You are the business analyst for your organization and are leading a presentation about a…