CCMP practice question 12 of 25
How does metric tracking support and sustain change that has been implemented?
Full set: 150 questionsMetric tracking is a critical component of the sustainment phase in change management. It provides objective, data-driven evidence of how the change is progressing against its intended outcomes and business results. This short-term evidence allows leadership and the change team to monitor adoption rates, proficiency levels, and performance improvements. By tracking progress, organizations can quickly identify areas where the change is not sticking, celebrate early wins to build momentum, and make informed decisions for corrective actions, all of which are essential activities to support and sustain the change over the long term.
A. Ensures staff are motivated to adopt change if they know their reactions will be tracked This is incorrect because tracking is primarily focused on performance and adoption metrics, not subjective "reactions." Furthermore, being tracked can sometimes create anxiety rather than motivation.
B. Provides content for a rewards and recognition program While metrics can inform a rewards program, this is a secondary use. The primary purpose of tracking is to measure overall progress and identify gaps, not solely to facilitate rewards.
C. Guides the development of policies and procedures Policies and procedures are typically developed during the planning and implementation phases of a change, not guided by post-implementation metric tracking, which serves to validate their effectiveness.
1. Association of Change Management Professionals (ACMP). (2019). The Standard for Change Management (Third Ed.).
Section 5.3, "Measure and Analyze Change Results": This section details the process of collecting and analyzing data to "assess the effectiveness of change management activities and progress toward desired outcomes." This directly supports the concept of providing evidence of progress and results (Answer D).
Section 5.4, "Reinforce and Sustain the Change": This section explains that the outputs from measurement (Section 5.3) are used to "implement reinforcement mechanisms" and "confirm that the change is sustained." This establishes the direct link between tracking metrics and the act of sustaining change.
2. Sirkin, H. L., Keenan, P., & Jackson, A. (2005). The Hard Side of Change Management. Harvard Business Review, 83(10), 108–118.
The article emphasizes the DICE framework, where "Effort" (E) involves measuring and monitoring progress frequently. It states, "Companies must rigorously track the progress of change programs... short-term results are the only proof that a change program is working." This directly validates that providing short-term evidence of progress (Answer D) is a key function of measurement in sustaining change.
3. MIT Sloan School of Management. (2004). 15.311 Organizational Processes, Handout: Implementing Change. MIT OpenCourseWare.
Page 4, "Refreezing: Reinforcing New Behaviors": The courseware explains that the "refreezing" or sustainment stage requires systems that measure performance and provide feedback. It states, "The new behavior must be congruent with the other systems in the organization... especially measurement systems." This highlights that metrics are a formal mechanism to provide the feedback (evidence) needed to reinforce and sustain new behaviors.
Keep practicing
Take the free CCMP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other CCMP practice questions
- Question 1What is the main purpose of assessing how well new change initiatives are aligned to the …
- Question 2What is the most significant element to look for when conducting an assessment of an orga…
- Question 3What document should provide guidance and best practices for future change initiatives?
- Question 4What is a recommended practice for aligning stakeholders around benefits and value of a c…
- Question 5What could be a significant input to the analysis of change objectives and in defining ne…
- Question 6The first two weeks of a large and complex change project is underway and things seem to …